Latest Update from CDL
APPROXIMATE PERCENTAGE COMPLETED(%) : 43%
EXPECTED ISSUANCE OF TOP / CSC* : Q2 2013
* Estimated date subject to changes
This is 30% more completed compared to Sept update and 1Q earlier to completion....the next 2Q should bring TOP much closer to 100%, perhaps should complete by 1Q 2013 optimistically.Originally Posted by mastrix
property price coming down silky slow. bo feeling jialat leh.Originally Posted by flagship74
.....some block almost reaching top floor at 23 going on 24...
![]()
Last edited by danntbt; 22-01-12 at 16:11.
...ya someone will be flagging white flag soon....seems to have quieten down....Originally Posted by sunrise
hahaOriginally Posted by danntbt
![]()
![]()
![]()
Anyone know what's the concrete structure in front of Blk 60? Sub-station? Belongs to Foresque or TH? It is not shown in any of their plans.Originally Posted by danntbt
shld belong to forest-kll i guessOriginally Posted by mastrix
![]()
...views taken from Foresque site, the foreground and middle ground belong to Foresque...Originally Posted by flagship74
Window frames are going up, with some units having glass panels up and Balcony frames.
Did anyone did a refinance after buying from the showflat sale?
stay low to avoid attack.Originally Posted by danntbt
Blocks that are at lowest completed floor are at 18th floor.
Thank you! Always waiting for you to load new photos!![]()
this development very spacious. nicely done.Originally Posted by mastrix
![]()
peace of mind.
Block 60 at 23rd story, 24 story partially completed.
All 4 blocks in view from Foresque site
Foresque with blue scaffolding cover in the background, seems like they are using a different construction method....no scaffold seen on TH as yet...
Block 62 with ground floor units glassed up and railings installed
Foresque have high soft storey (void). From the photo, we can see the super thick reinforcement.
just curious, will there be any concrete cover outside the 2nd sty room windows (other than the balcony slab) over the ground floor unit patio?
..think there is no overhang from 2nd story onwards, only on 1st storey.
...noticed that the construction progress on CDL updates site has regressed:
(http://www.cdl.com.sg/app/cdl/custom...p_progress.xml )
Tree House
Chestnut Avenue
Condo
35.1%
Q2 2013 as of 31 March 2012
from
42%
Q2 2013 as of 31 Dec 2011
....should be a mistake as expected TOP is still the same.
CDL Replied:
Dear >>>>>
Thank you for your email and our sincere apology for the confusion with regards to the percentage completed.
Due to a typo error, the percentage given last month was inaccurate. We have since taken note of the error and amended accordingly.
Should you require any further information pertaining to the project, you may contact us at 6877 1818 for assistance. Again, we would like to apologize for the error and inconvenience caused.
Thank you for your kind understanding.
Best Regards,
Regina Chia
Customer Service & Admin Dept
City Developments Limited
(Regn. No: 196300316Z)
http://www.cdl.com.sg
figure still at 35.1% and lower than the 42% in Dec Figure......this must be some kind of joke in terms of customer service.
no progress for the past 3 months. Haha
Lucky TOP still the same.
...the PR lady does not know her English....apparently her "last month" was 31 December!!!! She confirmed the current status is at 35.1% as in the latest figure so the 42% in Dec was wrong.....
hey! Passed by BKE today, saw one of the block, have its roof structure installed! Cannot see the other blocks.
....some painting are being done too....wondering when the adjacent development will be launched, likely to price upward of Foresque?Originally Posted by mastrix
painting? that's fast!Originally Posted by danntbt
ya...once that one launches...TH will "gain" again.![]()
the adjacent development must be landed house, malaysia developer sertia. launching end of the year.Originally Posted by danntbt
...don't think so, landed further the other side, this one has similar ratio as TH.Originally Posted by sunrise
![]()
Originally Posted by danntbt
yes, you are right. the landed is over the other site.
not much info on this plot of land. if belongs to HDB, then TH & foresque......
that land tender for sales already closed. Now waiting for developer to launch.....![]()
Block 60 behind is having the exterior plastered.....railings installed at lower floors.
Block 60 close-up with exterior plastering being applied and interior painted.
Full-height of Block 60, roofing pillar installed.
![]()