How come i can't see attachment? Pls advice thanks! New member
How come i can't see attachment? Pls advice thanks! New member
What you mean ? You mean you can't see the picture attach ? Is not if you are the owner of riviera 38 you can add us at fb .
https://www.facebook.com/condominium....3?ref=tn_tnmn
The Air con compressor have come in so we know they are doing the interior of the unit . Let hope they can finish fast
Noticed that landscaping has been put in at the sunbath deck.
Any new updated from riviera owner ?
The construction officer in the site say that they have hand over everything by April to allgreen developer !
I shd have pay 50 % not 55% .
So i can say that The electrical wiring, internal plastering, plumbing and installation of door and window frames of unit have completed. So another 5 percent is collected .
So what is the highest level that have collected 55% ? Any owner can reply me ?
They tested lights on the roof wings.
Yee ha! Did I tickle your funny bone?
Just wait and see. It's a surprise.
Yee ha! Did I tickle your funny bone?
The latest update for progressive payment
The progessive payment chart for Riviera 38
StagePayment under a standard payment scheme ( % of purchase price )
1. 10% -Completed
Upon the grant of Option to Purchase5%-10% (booking fee)
...
2. 20% -Completed
Upon signing of the Sale & Purchase Agreement or Within 8weeks from the Option date 20% less booking fee
...
3. 30% -Completed
Completion of foundation work 10%
4. 40% -Completed
Completion of reinforced concrete framework of unit 10%
5. 45%- Completed
Completion of brick walls of unit5%
6. 50% -Completed
Completion of roofing/ceiling of unit5%
7. 55% - level 6 to level 14
Completion of electrical wiring, internal plastering, plumbing and installation of door and window frames of unit 5%
8. 60% -
Completion of car park, roads and drains serving the housing project 5%
9. 85% -
Notice of Vacant Possession25%
9. On Completion Date
Any riviera owner have go to any interior design company for quotation for the interior design ? Any good interior company to introduce ? Can share in the forum .
Any new update ?
Is already march will southchina construction able to handover to all green properties by April ?
hi owner
Went to the site last sat , the progression of the exteriors is not much changes.
the level 2 car park temporary hostel for the worker to stay is remove .
Most of the exteriors is done , only the 3 bedder one of the bedroom they are fitting up the window glass .the window frame is all installed.
Found a a sign board at the entrance of the site written welcome a visitors call Dr ... i think is the bca personnel come check building for green mark award.
so dun know will it able to hand over to all green on April seem like a bit hard .