Thread: Downtown Line contractor goes bust, stops work on three stations

  1. #1
    Join Date
    Apr 2009
    Posts
    828

    Default Downtown Line contractor goes bust, stops work on three stations

    From http://www.sgcarmart.com/news/article.php?AID=8241

    "Work on three stations of the Downtown Line Stage 2 were halted on Wednesday after the main contractor, Alpine Bau GmbH, filed for insolvency. The stations affected are King Albert Park, Sixth Avenue, and Tan Kah Kee stations.

    Speaking to The Business Times, a spokesman for Land Transport Authority (LTA) said the current priority is to "ensure safety and security of the sites". He added, " We are looking at various options to appoint new completion contractors to take over the project, and ensure there is minimal impact on the timeline."

    The Downtown Line Stage 2 links the Bukit Timah corridor to Marina Bay, and is expected to be completed by 2015.

    Alpine Bau is Austria's second largest construction firm. It won the contract for design and construction of three stations and tunnel for Downtown Line Stage 2, which is valued at $670.74 million in 2009."

  2. #2
    Join Date
    Apr 2009
    Posts
    828

    Default

    Looks like the D21 and D10 people have to wait slightly longer to enjoy the DTL2...

  3. #3
    Join Date
    Oct 2010
    Posts
    4,739

    Default

    Quote Originally Posted by sunboy77
    .....

    Alpine Bau is Austria's second largest construction firm. It won the contract for design and construction of three stations and tunnel for Downtown Line Stage 2, which is valued at $670.74 million in 2009."
    oh no.
    murder of austria-hungary archduke lead to ww1
    failure of austria bank lead to great depression.
    now failure of austria construction firm will lead to .....?????

  4. #4
    Join Date
    May 2012
    Posts
    2,429

    Default

    That company is supposed to be Austria's second-biggest construction firm and can go bust.
    Scary leh!

  5. #5
    Join Date
    Apr 2009
    Posts
    828

    Default

    Europe is really not doing well....

  6. #6
    Join Date
    Oct 2011
    Posts
    10,829

    Default Work halts at 3 stations as contractor goes insolvent

    http://www.businesstimes.com.sg/prem...lvent-20130621

    Published June 21, 2013

    Work halts at 3 stations as contractor goes insolvent

    By Mindy Tan


    [SINGAPORE] Work ground to a halt at three upcoming train stations on Wednesday after Alpine Bau GmbH, the main contractor for them, filed for insolvency. It had been working on building Downtown Line Stage 2's King Albert Park, Sixth Avenue, and Tan Kah Kee Stations.

    "LTA's immediate priority is to ensure the safety and security of the sites. Measures are being put in place to safeguard the sites and equipment," said a spokesperson for the Land Transport Authority (LTA), when contacted yesterday.

    "We are looking at various options to appoint new completion contractors to take over the project," added the spokesperson.

    "LTA will work closely with the appointed completion contractors to continue engaging the existing subcontractors to ensure minimal impact on the timeline."

    Downtown Line Stage 2, which will link the Bukit Timah corridor to Marina Bay, is expected to be up by 2015.

    Alpine Bau, Austria's second biggest construction firm, won the contract for the design and construction of the three stations and tunnels along Downtown Line Stage 2, valued at $670.74 million, in 2009. It has since been plagued by financial troubles, however, which led to it filing for insolvency on Wednesday.

    Reuters had earlier reported that the insolvent construction unit of Spanish group FCC has liabilities of up to 2.6 billion euros, according to Austrian creditor agency KSV.

    In the latest update on Alpine's website, the company said that "efforts to reach an out of court settlement for the restructuring of Alpine Group have, contrary to expectations, and despite significant support by financing partners and intensive efforts by the shareholder, not been successful and thus been terminated."

    "In the course of these proceedings a concept has been developed by experienced subject-matter-experts to save parts of the Alpine Group and related employees as well as subcontractors. This concept shall be assessed and implemented in the next weeks by the competent administrators," it added.

  7. #7
    Join Date
    May 2009
    Posts
    1,449

    Default

    Quote Originally Posted by princess_morbucks
    That company is supposed to be Austria's second-biggest construction firm and can go bust.
    Scary leh!
    The bigger, the more easily to bust... Big company and big overhead... Properly they have more managers then engineers...

Similar Threads

  1. Four contracts worth S$1.04 billion for three Thomson Line stations and for the line'
    By iwant2buyproperty in forum Singapore Private Condominium Property Discussion and News
    Replies: 0
    -: 18-10-13, 13:28
  2. Businesses cheer new Downtown Line stations
    By reporter2 in forum HDB, EC, commercial and industrial property discussion
    Replies: 0
    -: 09-10-13, 16:23
  3. Six stations of Downtown Line to open on Dec 22
    By reporter2 in forum HDB, EC, commercial and industrial property discussion
    Replies: 0
    -: 08-10-13, 13:35
  4. Downtown Line 2 (Bukit Timah Line)
    By moneymatters in forum HDB, EC, commercial and industrial property discussion
    Replies: 11
    -: 18-07-08, 10:55
  5. Five stops planned for first phase of Downtown MRT line
    By mr funny in forum HDB, EC, commercial and industrial property discussion
    Replies: 0
    -: 15-03-07, 14:04

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •