  1. #1351
    Join Date
    Jul 2011
    Posts
    398

    Default

    Quote Originally Posted by joecool View Post
    I'm personally very annoyed by this myself. The FEO agents was so sure when I first bought the place that the place would be ready by 2014, but I'm not so sure now. If you go to the front of the construction site and check out the board, it actually says 2016 now. I hope that's just a very conservative estimation.
    That's not good, delay further to 2016?

    The FEO agent also informed me estimated TOP around 3rd quarter 2014 when I bought. Looking at the progress, doubt it's going to happen. Should be glad if can be ready by first or second quarter 2015.

    Btw, anyone knows if the future Kaki Bukit Mrt is within walking distance? Looking at the map, seems doable.

  2. #1352
    Join Date
    Sep 2013
    Posts
    12

    Default

    Quote Originally Posted by GSLJ View Post
    That's not good, delay further to 2016?

    The FEO agent also informed me estimated TOP around 3rd quarter 2014 when I bought. Looking at the progress, doubt it's going to happen. Should be glad if can be ready by first or second quarter 2015.

    Btw, anyone knows if the future Kaki Bukit Mrt is within walking distance? Looking at the map, seems doable.
    Probably about 600 metres. the next nearest is Ubi about 800 metres to 1 km. For Kaki Bukit MRT looks like mostly uphill from EH.

  3. #1353
    Join Date
    Feb 2011
    Posts
    8,926

    Default

    with SSD, still gain?

    7 JAN 2014 200 JALAN EUNOS #XX-XX 538sqft 1,189psf 16 SEP 2011 1,001psf 101,144 844d 7.7%
    Ride at your own risk !!!

  4. #1354
    Join Date
    Feb 2013
    Posts
    10

    Default

    Drove past the construction area again and happy to note that the centremost portion of the land has work going on already.

    Hope its a sign of better (and faster) things to come!

    Happy CNY all and Huat Ah!!

  5. #1355
    Join Date
    Nov 2013
    Posts
    54

    Default

    Quote Originally Posted by phantom_opera View Post
    with SSD, still gain?

    7 JAN 2014 200 JALAN EUNOS #XX-XX 538sqft 1,189psf
    16 SEP 2011 1,001psf 101,144 844d 7.7%
    Yes. earned less than $2000 if SGaporean's 2nd property.

  6. #1356
    Join Date
    Oct 2012
    Posts
    59

    Default Building in progress

    Quote Originally Posted by deedee28 View Post
    Drove past the construction area again and happy to note that the centremost portion of the land has work going on already.

    Hope its a sign of better (and faster) things to come!

    Happy CNY all and Huat Ah!!
    Thanks for the update.

    Drove by near the site myself and was very pleased (even though I sound like a slavedriver) that the construction was underway at night (it was around 8pm). Seemed like there was some progress since my last visit a few weeks ago.

  7. #1357
    Join Date
    Feb 2013
    Posts
    10

    Default

    There's nothing slavedriver-ish about wishing your roof over your head will come sooner than later

    Seriously.... taking too long

    It doesn't help that I live in the area and get to see the construction every other time.

  8. #1358
    Join Date
    Oct 2012
    Posts
    59

    Default Too Long

    Quote Originally Posted by deedee28 View Post
    There's nothing slavedriver-ish about wishing your roof over your head will come sooner than later

    Seriously.... taking too long

    It doesn't help that I live in the area and get to see the construction every other time.
    I hear you

    This is going to be my first home (that I actually own!) and I'm having to set back my plans to accommodate their delay. First, they say mid 2014 (my bad for actually believing anything that a salesman would say). Then, if you take Far East's newsletter for what its worth, Q3 2014 to Q3 2015 depending on the issue. But if you go to the actual site, it's different, and if you look at the progress so far on Far East's website, it's Q4 2017.

  9. #1359
    Join Date
    Aug 2009
    Posts
    551

    Default





    This is NOT acceptable!

  10. #1360
    Join Date
    Aug 2009
    Posts
    551

    Default

    http://www.fareast.com.sg/~/media/pr...1%20Feb%202014

    Last 9 out of 748 units left (98.8% sold).

  11. #1361
    Join Date
    Jul 2011
    Posts
    398

    Default

    Quote Originally Posted by PropertyHound View Post
    Probably about 600 metres. the next nearest is Ubi about 800 metres to 1 km. For Kaki Bukit MRT looks like mostly uphill from EH.
    Thanks for your reply, I went to survey the site.

    From condo entrance, uphill till the main Bedok Reservoir road, cross over and downhill at Jalan Tenaga till the Mrt. Another route would be to exit near tennis court side, using the Siglap park connector to reach Bedok North Mrt.

    Both routes are quite a distance, only doable if it's a weekend casual walk.

  12. #1362
    Join Date
    Jul 2011
    Posts
    398

    Default

    Updates for all owners.

    The board on site states expected TOP at Dec 2016.

    So I made a call to FEO to enquire on the progress and if there's any reasons for delay. The reply i got was there isn't any delay and the duration required is normal. Estimated TOP to be around 3rd/4th 2015.

    Upon further enquiry on why the FEO construction progress update states TOP 1st Q 2017, they are unaware of this. So the reply given doesn't really sound too convincing to me.


  13. #1363
    Join Date
    Aug 2009
    Posts
    551

    Default

    Based on S&P docs, FEO is required to deliver vacant possesstion of the unit to the buyer by 31 Dec 2016.

    Failure to do so, FEO has to pay liquidated damages (10% per annum) to the buyer.

  14. #1364
    Join Date
    Aug 2009
    Posts
    551

    Default

    Construction Progress Update has been rectified.



    So it is still on-track for Q3 2015 delivery.

    Only 4% SSD when TOP! Cheers.

  15. #1365
    Join Date
    Jul 2011
    Posts
    398

    Default

    From FEO website-

    2 big units sold, balance 5units and 2TH.(99% sold)

    http://www.fareast.com.sg/~/media/pr...6%20Feb%202014

    ANNOUNCEMENTS
    Final 3 units of 4-bedroom available.
    Prices from $1,450 psf.*
    *Terms and conditions apply. Subject to changes without prior notice. For a limited time period only.


  16. #1366
    Join Date
    Oct 2012
    Posts
    59

    Default

    Quote Originally Posted by Tripp View Post




    This is NOT acceptable!
    This is BULLSHIT!

  17. #1367
    Join Date
    Feb 2013
    Posts
    10

    Default

    Just got my notification of 10% loan drawdown like last week.

    Bittersweet feeling.

  18. #1368
    Join Date
    Oct 2011
    Posts
    1,668

    Default

    Quote Originally Posted by deedee28 View Post
    Just got my notification of 10% loan drawdown like last week.

    Bittersweet feeling.
    Wow eu really construction very slow now just another 10 % this project launch since jun 2011

  19. #1369
    Join Date
    Jul 2011
    Posts
    398

    Default

    Update for all owners.

    Received payment request for the next 5%- ceiling completed.
    The cert for stage completion also indicates that the internal is also completed.

    So 2 more payments to TOP, progressing well!

  20. #1370
    Join Date
    Feb 2013
    Posts
    10

    Default

    Quote Originally Posted by GSLJ View Post
    Update for all owners.

    Received payment request for the next 5%- ceiling completed.
    The cert for stage completion also indicates that the internal is also completed.

    So 2 more payments to TOP, progressing well!
    Congratulations! Best news i've read in a long time regarding this project. Hope its a sign for the other stacks also. Cycled by again with that wistful look

  21. #1371
    Join Date
    Apr 2008
    Posts
    226

    Default

    Quote Originally Posted by GSLJ View Post
    Update for all owners.

    Received payment request for the next 5%- ceiling completed.
    The cert for stage completion also indicates that the internal is also completed.

    So 2 more payments to TOP, progressing well!
    Yes. Received my 2nd 5% payment last week. Two more 5% before TOP. Based on the duration between 1st and 2nd 5% payment of 4 months, it will be interpolated to 8 more months to complete the last payment. So I will predict that TOP should be around mid 2015.

  22. #1372
    Join Date
    Oct 2012
    Posts
    59

    Default Insulting!

    Quote Originally Posted by GSLJ View Post
    Updates for all owners.

    The board on site states expected TOP at Dec 2016.

    So I made a call to FEO to enquire on the progress and if there's any reasons for delay. The reply i got was there isn't any delay and the duration required is normal. Estimated TOP to be around 3rd/4th 2015.

    Upon further enquiry on why the FEO construction progress update states TOP 1st Q 2017, they are unaware of this. So the reply given doesn't really sound too convincing to me.

    I find it personally insulting that they are treating us like fools. I distinctively recall their sales team selling it to me (and my wife and my mother-in-law who tagged along) when we first bought the unit that the unit would be ready by 2014. Now they're saying "there isn't any delay and the duration is normal".

    I suppose this is a valuable lesson for the future and to anyone else who is reading these forums.

  23. #1373
    Join Date
    Oct 2012
    Posts
    59

    Default

    Quote Originally Posted by GSLJ View Post
    Update for all owners.

    Received payment request for the next 5%- ceiling completed.
    The cert for stage completion also indicates that the internal is also completed.

    So 2 more payments to TOP, progressing well!
    Thanks, buddy. Good to know. I've yet to receive notice but expect it'll be coming anytime soon.

  24. #1374
    Join Date
    Mar 2014
    Posts
    1

    Default Happy April Fools day

    Happy April Fools day, hopefully they are not treating us like fools and construction could be faster!

  25. #1375
    Join Date
    Feb 2013
    Posts
    10

    Default

    Any updates from anyone? Took a leisurely ride to the construction site again and happy to report that works in the middle have been coming along nicely though nothing close to the promise we might move in by 2014 end.

    Fingers crossed until cramped already.

  26. #1376
    Join Date
    Aug 2011
    Posts
    13

    Default

    Bank drawdown for the 3rd 5% payment.
    Fast & furious now.

    Quote Originally Posted by propertyinvestor View Post
    Yes. Received my 2nd 5% payment last week. Two more 5% before TOP. Based on the duration between 1st and 2nd 5% payment of 4 months, it will be interpolated to 8 more months to complete the last payment. So I will predict that TOP should be around mid 2015.

  27. #1377
    Join Date
    Jul 2011
    Posts
    398

    Default

    Quote Originally Posted by deedee28 View Post
    Congratulations! Best news i've read in a long time regarding this project. Hope its a sign for the other stacks also. Cycled by again with that wistful look
    Thanks, you are staying around the area?

    Quote Originally Posted by deedee28 View Post
    Any updates from anyone? Took a leisurely ride to the construction site again and happy to report that works in the middle have been coming along nicely though nothing close to the promise we might move in by 2014 end.

    Fingers crossed until cramped already.
    Nothing much to update, the towers are still covered with green canvas.

    But can see most of the towers have reach roof level.

  28. #1378
    Join Date
    Jul 2011
    Posts
    398

    Default

    Quote Originally Posted by joecool View Post
    I find it personally insulting that they are treating us like fools. I distinctively recall their sales team selling it to me (and my wife and my mother-in-law who tagged along) when we first bought the unit that the unit would be ready by 2014. Now they're saying "there isn't any delay and the duration is normal".

    I suppose this is a valuable lesson for the future and to anyone else who is reading these forums.
    Hi bro,

    I guess the cut down on foreign labour could be a contributing factor.
    This project is on a huge piece of land with 700+ units, so will take some time.
    If can TOP next year, would still be within 4years to completion.
    Happy with that.

    Quote Originally Posted by joecool View Post
    Thanks, buddy. Good to know. I've yet to receive notice but expect it'll be coming anytime soon.
    You should be expecting to receive notice again soon!

  29. #1379
    Join Date
    Jul 2011
    Posts
    398

    Default

    Quote Originally Posted by igoeast View Post
    Bank drawdown for the 3rd 5% payment.
    Fast & furious now.
    Thanks for update.

    We are getting there, next year TOP!

    Quote Originally Posted by GSLJ View Post
    Update for all owners.

    Received payment request for the next 5%- ceiling completed.
    The cert for stage completion also indicates that the internal is also completed.

    So 2 more payments to TOP, progressing well!
    Quote Originally Posted by propertyinvestor View Post
    Yes. Received my 2nd 5% payment last week. Two more 5% before TOP. Based on the duration between 1st and 2nd 5% payment of 4 months, it will be interpolated to 8 more months to complete the last payment. So I will predict that TOP should be around mid 2015.
    Update for all owners.

    As expected, payment request again just a month after ceiling completion.
    Received payment request for next 5%- internal completed.

    Just one more 5% payment for carpark, roads and we have TOP!

  30. #1380
    Join Date
    Apr 2008
    Posts
    226

    Default

    Quote Originally Posted by GSLJ View Post
    Thanks for update.

    We are getting there, next year TOP!



    Update for all owners.

    As expected, payment request again just a month after ceiling completion.
    Received payment request for next 5%- internal completed.

    Just one more 5% payment for carpark, roads and we have TOP!
    Wow, look like the TOP may be earlier. Possible by end of this year? Cheers.

Similar Threads

  1. Replies: 0
    -: 07-11-19, 18:32
  2. Sky Habitat - Bishan
    By testtest in forum Central North
    Replies: 2342
    -: 20-09-18, 15:58
  3. Replies: 12
    -: 12-05-14, 18:09
  4. Replies: 49
    -: 04-01-13, 15:43
  5. 70% of sky habitat snapped up in a day!
    By FilthyRich in forum Singapore Private Condominium Property Discussion and News
    Replies: 585
    -: 12-05-12, 20:01

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •