Sea Esta
07-09-14, 01:17
Construction Progress - 6th September 2014

6th September 2014 - Close Up - Roof Level of Block 18, Block 20, Block 22, Block 26 and Block 28 completed plus Roof Level of Block 30 in progress.
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xaf1/v/t1.0-9/10665776_560458584060808_4029668846975932424_n.jpg?oh=8087ff43d3c4ff4f12eca7949aeef965&oe=54A3871B&__gda__=1419664298_97c8032134fba029c0a4d06d8e48a437

6th September 2014 - Panoramic View.
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10628139_560458670727466_3857199230918091295_n.jpg?oh=935e4d3f57abbdbe9bbd83ea444bbf2e&oe=5487EAE3&__gda__=1419576938_21b9f2d0f0b599d202e42cbf398f9f4c

6th September 2014 - Sea Esta from Pasir Ris Link.
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10660177_560458767394123_7901141762562441029_n.jpg?oh=51c8b7498eb139b85e234ab1da5a12fc&oe=548B736A&__gda__=1418090194_36becf16bfa6247a0acc63870521c553

6th September 2014 - Block 18 is at Roof Level.
https://scontent-a.xx.fbcdn.net/hphotos-xaf1/v/t1.0-9/10418429_560458854060781_6070898515255495577_n.jpg?oh=896394b6d5fe5538b81e690b3f99fb78&oe=545AE5F1

6th September 2014 - Block 20 is at Roof Level.
https://scontent-a.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10349884_560458974060769_4857040228234084711_n.jpg?oh=9a9acc153702a9d725bd3c36dcc95dfc&oe=548825E6

6th September 2014 - Block 20 is at Roof Level. (Alternate View)
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10423889_560459077394092_4331752311887628684_n.jpg?oh=c192c38a7bf13d89ee641e7b580da845&oe=5482F496&__gda__=1418411807_e91d70cbb0d0872601fb5948ae8efef3

6th September 2014 - Block 22 is at Roof Level.
https://scontent-b.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10646772_560459310727402_3743261876288482670_n.jpg?oh=1ab27b573c34d84cd695834cb2d858c3&oe=54A7225C

6th September 2014 - Block 22 is at Roof Level. (Alternate View)
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10616078_560459427394057_7535720677852851931_n.jpg?oh=4a9966d1c9d9b84a891204b135f0c812&oe=54A60EBD&__gda__=1419782241_8bf461b44b7f5abb74be22d817032930

6th September 2014 - Block 26 is at Roof Level.
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10629710_560459524060714_1547007170801720714_n.jpg?oh=45547849e212dfa005570c80b3596735&oe=54A9B257&__gda__=1419850718_57b234a1f22f2e44df3bd178ea75499d

6th September 2014 - Block 28 is at Roof Level.
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10653607_560459654060701_5480354860819976055_n.jpg?oh=7a856e2d2a6211f24f1963bac88f017c&oe=54930D48&__gda__=1419517844_bf6701d09982b9325eb0c5917c852d8f

6th September 2014 - Block 30 is at Level 13.
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10557415_560459800727353_1076908496507451431_n.jpg?oh=e272427a6f2d0538f24930cdff4c4067&oe=5490430B&__gda__=1419891123_1d4e13c897fe4c2d8f9ebacfc0fdb7af

6th September 2014 - Block 30 is at Level 13. (Alternate View)
https://scontent-a.xx.fbcdn.net/hphotos-xaf1/v/t1.0-9/10384098_560459920727341_2764740643933350431_n.jpg?oh=a4720a3f00591ce0989676438fb0831b&oe=5483803B

6th September 2014 - Block 24, the club house is completed.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xfa1/v/t1.0-9/10676381_560460074060659_837224037558979433_n.jpg?oh=11db4003cf2d0beb5d7f7c3d958aaa74&oe=54952728&__gda__=1418188152_ac999f08c61c9d852d2e8275daf0e4c4

6th September 2014 - Sea Esta from Ripple Bay's Construction Site Main Gate.
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10689918_560460237393976_2202104665755958127_n.jpg?oh=857982fb9434fa6ae3c61ed69cb85b6f&oe=5489EB87&__gda__=1418019598_9ddf489a5aef833826b2eab4e99b21bf

6th September 2014 - Half of Pasir Ris Link is now opened to traffic (1).
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10416571_560460367393963_8377491686128913470_n.jpg?oh=66d8411d564217d7a269f0a95637cb55&oe=549664A5&__gda__=1418600236_464f254169e4f1a3ff5ec27063b6a364

6th September 2014 - Half of Pasir Ris Link is now opened to traffic (2).
https://scontent-b.xx.fbcdn.net/hphotos-xfp1/v/t1.0-9/10614151_560460484060618_3743861863814583251_n.jpg?oh=7546865e3eb36c27276e996fd1f526b6&oe=54898291

6th September 2014 - Half of Pasir Ris Link is now opened to traffic (3).
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xfa1/v/t1.0-9/10687095_560460557393944_5589256584353436265_n.jpg?oh=66e07890a49be68784fe4679ad8650df&oe=549D6C8C&__gda__=1419872698_b1b81ef8e304eb04a3888b08b53e618a

6th September 2014 - Half of Pasir Ris Link is now opened to traffic (4).
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10632760_560460610727272_4453850976430417059_n.jpg?oh=c9c2dce5de7f772da97587884c8d5af4&oe=5494007F&__gda__=1419773127_e3a658ae9f2751e5c3dde02b4ad2a978

6th September 2014 - Seastrand sign are up. TOP coming soon?
https://fbcdn-sphotos-a-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10007473_560460734060593_114709520314102268_n.jpg?oh=f7bfcd29b3fff779ebf5f35a5efaf14b&oe=548FA445&__gda__=1419170270_ba4a6a1731a6befc2563ca41943410f6

Sea Esta
07-09-14, 01:18
:cheers1:...my guess is Mar 2015 :hornybastard: !

My guess is May 2015. :beguiled:

DPan
07-09-14, 08:56
My guess is May 2015. :beguiled:

Yes, agree. May/June more likely

CondoWE
07-09-14, 12:14
Construction Progress - 6th September 2014

6th September 2014 - Close Up - Roof Level of Block 18, Block 20, Block 22, Block 26 and Block 28 completed plus Roof Level of Block 30 in progress.
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xaf1/v/t1.0-9/10665776_560458584060808_4029668846975932424_n.jpg?oh=8087ff43d3c4ff4f12eca7949aeef965&oe=54A3871B&__gda__=1419664298_97c8032134fba029c0a4d06d8e48a437

6th September 2014 - Panoramic View.
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10628139_560458670727466_3857199230918091295_n.jpg?oh=935e4d3f57abbdbe9bbd83ea444bbf2e&oe=5487EAE3&__gda__=1419576938_21b9f2d0f0b599d202e42cbf398f9f4c

6th September 2014 - Sea Esta from Pasir Ris Link.
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10660177_560458767394123_7901141762562441029_n.jpg?oh=51c8b7498eb139b85e234ab1da5a12fc&oe=548B736A&__gda__=1418090194_36becf16bfa6247a0acc63870521c553

6th September 2014 - Block 18 is at Roof Level.
https://scontent-a.xx.fbcdn.net/hphotos-xaf1/v/t1.0-9/10418429_560458854060781_6070898515255495577_n.jpg?oh=896394b6d5fe5538b81e690b3f99fb78&oe=545AE5F1

6th September 2014 - Block 20 is at Roof Level.
https://scontent-a.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10349884_560458974060769_4857040228234084711_n.jpg?oh=9a9acc153702a9d725bd3c36dcc95dfc&oe=548825E6

6th September 2014 - Block 20 is at Roof Level. (Alternate View)
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10423889_560459077394092_4331752311887628684_n.jpg?oh=c192c38a7bf13d89ee641e7b580da845&oe=5482F496&__gda__=1418411807_e91d70cbb0d0872601fb5948ae8efef3

6th September 2014 - Block 22 is at Roof Level.
https://scontent-b.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10646772_560459310727402_3743261876288482670_n.jpg?oh=1ab27b573c34d84cd695834cb2d858c3&oe=54A7225C

6th September 2014 - Block 22 is at Roof Level. (Alternate View)
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10616078_560459427394057_7535720677852851931_n.jpg?oh=4a9966d1c9d9b84a891204b135f0c812&oe=54A60EBD&__gda__=1419782241_8bf461b44b7f5abb74be22d817032930

6th September 2014 - Block 26 is at Roof Level.
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10629710_560459524060714_1547007170801720714_n.jpg?oh=45547849e212dfa005570c80b3596735&oe=54A9B257&__gda__=1419850718_57b234a1f22f2e44df3bd178ea75499d

6th September 2014 - Block 28 is at Roof Level.
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10653607_560459654060701_5480354860819976055_n.jpg?oh=7a856e2d2a6211f24f1963bac88f017c&oe=54930D48&__gda__=1419517844_bf6701d09982b9325eb0c5917c852d8f

6th September 2014 - Block 30 is at Level 13.
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10557415_560459800727353_1076908496507451431_n.jpg?oh=e272427a6f2d0538f24930cdff4c4067&oe=5490430B&__gda__=1419891123_1d4e13c897fe4c2d8f9ebacfc0fdb7af

6th September 2014 - Block 30 is at Level 13. (Alternate View)
https://scontent-a.xx.fbcdn.net/hphotos-xaf1/v/t1.0-9/10384098_560459920727341_2764740643933350431_n.jpg?oh=a4720a3f00591ce0989676438fb0831b&oe=5483803B

6th September 2014 - Block 24, the club house is completed.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xfa1/v/t1.0-9/10676381_560460074060659_837224037558979433_n.jpg?oh=11db4003cf2d0beb5d7f7c3d958aaa74&oe=54952728&__gda__=1418188152_ac999f08c61c9d852d2e8275daf0e4c4

6th September 2014 - Sea Esta from Ripple Bay's Construction Site Main Gate.
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10689918_560460237393976_2202104665755958127_n.jpg?oh=857982fb9434fa6ae3c61ed69cb85b6f&oe=5489EB87&__gda__=1418019598_9ddf489a5aef833826b2eab4e99b21bf

6th September 2014 - Half of Pasir Ris Link is now opened to traffic (1).
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10416571_560460367393963_8377491686128913470_n.jpg?oh=66d8411d564217d7a269f0a95637cb55&oe=549664A5&__gda__=1418600236_464f254169e4f1a3ff5ec27063b6a364

6th September 2014 - Half of Pasir Ris Link is now opened to traffic (2).
https://scontent-b.xx.fbcdn.net/hphotos-xfp1/v/t1.0-9/10614151_560460484060618_3743861863814583251_n.jpg?oh=7546865e3eb36c27276e996fd1f526b6&oe=54898291

6th September 2014 - Half of Pasir Ris Link is now opened to traffic (3).
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xfa1/v/t1.0-9/10687095_560460557393944_5589256584353436265_n.jpg?oh=66e07890a49be68784fe4679ad8650df&oe=549D6C8C&__gda__=1419872698_b1b81ef8e304eb04a3888b08b53e618a

6th September 2014 - Half of Pasir Ris Link is now opened to traffic (4).
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10632760_560460610727272_4453850976430417059_n.jpg?oh=c9c2dce5de7f772da97587884c8d5af4&oe=5494007F&__gda__=1419773127_e3a658ae9f2751e5c3dde02b4ad2a978

6th September 2014 - Seastrand sign are up. TOP coming soon?
https://fbcdn-sphotos-a-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10007473_560460734060593_114709520314102268_n.jpg?oh=f7bfcd29b3fff779ebf5f35a5efaf14b&oe=548FA445&__gda__=1419170270_ba4a6a1731a6befc2563ca41943410f6
Seem like the construction 👷 progress is slowing down....Sigh!

081828
07-09-14, 12:25
Are the interiors being work on currently? At which stage of the progress payment is it at now?

CondoWE
07-09-14, 14:34
Are the interiors being work on currently? At which stage of the progress payment is it at now?

Paid 45%....but the construction progress of my block like 55%..:beguiled:!

Sunnielee
08-09-14, 12:00
Anyone notice Parc Olympia's website? Their developer posted expected date of completion 1Q 2015. But the construction progress a few months behind of Sea Esta...

http://nc.kohbrothers.com/project-schedules-parc-olympia

Mike88
08-09-14, 18:18
Hi Everyone,

I am new to this forum. Wonder if anyone has started looking for interior designer?
If so, any good recommend?

Sat Han
08-09-14, 21:12
i heard, it take about a month to pass the keys.

v_esta
08-09-14, 22:29
Hi Everyone,

I am new to this forum. Wonder if anyone has started looking for interior designer?
If so, any good recommend?

Hi Mike88,

Ummm... we are not sure about the TOP date so yet to "shop" for interior designer.
You so fast looking around for interior designer??

:welcoming:

v_esta
08-09-14, 22:33
Anyone notice Parc Olympia's website? Their developer posted expected date of completion 1Q 2015. But the construction progress a few months behind of Sea Esta...

http://nc.kohbrothers.com/project-schedules-parc-olympia

Wah, how come theirs can TOP faster with slower construction progress??

Sea Esta
08-09-14, 23:39
Wah, how come theirs can TOP faster with slower construction progress??

The only reason I can think of is Sea Esta has a smaller land size. The fact that Straits Constructions got to build from inside out aka build block 20 and 22 first and block 18 and 30 last indicated they dun have a lot of land to manoeuvre.

Parc Olympia might not have this issue and all their blocks can be build together n progress together. Each of their block has lesser floors compared to Sea Esta thus they can complete faster.

I might be wrong.

radha08
09-09-14, 00:45
huat ahhhhh


http://www.propertyguru.com.sg/listing/18335892/for-sale-sea-esta

http://www.propertyguru.com.sg/listing/17732652/for-sale-sea-esta

Mike88
09-09-14, 14:50
Hi V-esta,

Just looking for good ideas and designs for our new home. So that it will not be a rush renovation.
After site visit, look like 1st quarter to hand over the key.

Looks like Seastrand is preparing to hand over the keys by this quarter.

Myeast
09-09-14, 15:35
Hi Mike88,

I am also searching around this moment, you may get some ideas from "Arc @ Tampines Reno Carrots" at facebook.

Frste
15-09-14, 15:57
huat ahhhhh


http://www.propertyguru.com.sg/listing/18335892/for-sale-sea-esta

http://www.propertyguru.com.sg/listing/17732652/for-sale-sea-esta



Wah huat huat!

CondoWE
28-09-14, 00:10
Any new update of the construction progress this week?

Sea Esta
28-09-14, 05:06
27th September 2014 - Construction Progress
All cranes removed except Block 30....


27th September 2014 - Close Up - Block 18, Block 20, Block 22, Block 26, Block 28 and Block 30 completed.
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xaf1/v/t1.0-9/10703615_570525976387402_4404644702896991564_n.jpg?oh=9ba0de9e0a1a67ce4bb57abb0a1944cc&oe=54B7F72D&__gda__=1417970076_cc2fc8ab6bfe883b1153a64a749f01bf

27th September 2014 - Panoramic View.
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/1622092_570526123054054_6522424322555366420_n.jpg?oh=bf924a744647245f31385d5c41f3101d&oe=54C799AF&__gda__=1417826790_93afb7efe87ce057553e754d92138d16

27th September 2014 - Sea Esta from Pasir Ris Link.
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10665160_570526179720715_4934521414331755746_n.jpg?oh=14bc9a4d440506a00fc74d796f94bc1b&oe=54840211&__gda__=1421555881_8d4946e8f1662c055a0635a45b1aaf67

27th September 2014 - Block 18 is at Roof Level.
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xaf1/v/t1.0-9/10703696_570526313054035_2481542917199689221_n.jpg?oh=57182c2c36d352eccb31f6cbc473c855&oe=54D068FD&__gda__=1422836812_532afc9b37b379a3f5677fcf708865a0

27th September 2014 - Block 20 is at Roof Level.
https://fbcdn-sphotos-a-a.akamaihd.net/hphotos-ak-xfa1/v/t1.0-9/10696333_570526389720694_6722435921239752990_n.jpg?oh=3ddb0058a4aa83ac854997a4707d36d3&oe=54C9D944&__gda__=1422924658_abbae770384b35db64773a10628029cb

27th September 2014 - Block 20 is at Roof Level. (Alternate View)
https://scontent-a.xx.fbcdn.net/hphotos-xaf1/v/t1.0-9/10253907_570526483054018_6168321205573760214_n.jpg?oh=27229a8eb0400e32ec7157b1aa780164&oe=54CDFEE9

27th September 2014 - Block 22 is at Roof Level and two coat of painting.
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10636300_570526579720675_112220415670375010_n.jpg?oh=074cf9902a60fd580a23fdcfbf4c3ada&oe=54BDFC05&__gda__=1418452044_9b0794b9a2064b7bc0f12e93d93abcbc

27th September 2014 - Block 22 is at Roof Level. (Alternate View)
https://scontent-b.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10473045_570526743053992_3685908438925708173_n.jpg?oh=2c18719cb069b9d88e3ba4b160830f2d&oe=54BDBE23

27th September 2014 - Block 26 is at Roof Level.
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10672225_570526876387312_8873888864352677719_n.jpg?oh=bfd17744cc204240ef1ab44327b67e64&oe=548A8B0A&__gda__=1422553731_eab6d760e3e2399729cf0623dff35b36

27th September 2014 - Block 28 is at Roof Level.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10404399_570527036387296_6047078176581207719_n.jpg?oh=b51ca7e14e640cf59223e025854ec51c&oe=54C19ABC&__gda__=1421759702_4c063046b36359409799ad9d25ad947c

27th September 2014 - Block 30 is at Roof Level.
https://scontent-a.xx.fbcdn.net/hphotos-xfp1/v/t1.0-9/1095001_570527133053953_6044583587029986207_n.jpg?oh=dcc39a5faaee22b2a76d553c0d01510e&oe=548CC872

27th September 2014 - Block 30 is at Roof Level. (Alternate View)
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10334414_570527206387279_6004942370687878793_n.jpg?oh=6c4af1706206f09a5883f9901f573107&oe=548B788E&__gda__=1421453063_5700e8eed828c0ca99609b9d7f2d1ab0

27th September 2014 - Block 24, the club house is completed.
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10685544_570527296387270_3237152658563374305_n.jpg?oh=e4750896bde90677015c9054de242e93&oe=54C54934&__gda__=1417992332_a8e02d5086f88e08c7a125f0b5dd5531

27th September 2014 - Sunset Pool?
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10649871_570527366387263_2876753063856827911_n.jpg?oh=46f9632f9050b4e5277ebe0e4d3a8858&oe=54D0A587&__gda__=1422289727_679cd065e6451a5d2a8fc5bfc655eeee

CondoWE
28-09-14, 09:17
Thanks bro for update...:cheers4: !

From the photo can't really differential the 2 coat of paint, White and light brown?

Sea Esta
28-09-14, 10:55
Thanks bro for update...:cheers4: !

From the photo can't really differential the 2 coat of paint, White and light brown?

Block 22. Noticed workers painting a new colour over the original white coat.

v_esta
28-09-14, 12:48
Here's a few inside shots... :)

Thermofisher
28-09-14, 13:24
The color of buildings look like HDB...

CondoWE
28-09-14, 13:48
The color of buildings look like HDB...


Block 22. Noticed workers painting a new colour over the original white coat.


What colour is the new paint?

v_esta
28-09-14, 14:08
What colour is the new paint?

Seems to me it's darker brown than Watercolors but lighter than Seastrand. Let's wait till they complete everything and finish painting... It'll be clearer then. :)

CondoWE
28-09-14, 16:14
Seems to me it's darker brown than Watercolors but lighter than Seastrand. Let's wait till they complete everything and finish painting... It'll be clearer then. :)

White and dark Brown....Zen colour...:glee:!

v_esta
28-09-14, 17:00
White and dark Brown....Zen colour...:glee:!

Yup, I guess you can say it's pretty zen! Haha...

Yuki
29-09-14, 07:51
Congrats. When is the target Top?

DPan
29-09-14, 20:35
My bank have just pay another 5%( Electrical wiring, internal plastering, plumbing and installation of door and window frames )
to the developer.
Any bro also receive the letter ?

CondoWE
29-09-14, 20:50
My bank have just pay another 5%( Electrical wiring, internal plastering, plumbing and installation of door and window frames )
to the developer.
Any bro also receive the letter ?

How many % have you paid till date include this 5%?

1984
29-09-14, 22:00
My bank have just pay another 5%( Electrical wiring, internal plastering, plumbing and installation of door and window frames )
to the developer.
Any bro also receive the letter ?

Mine only at stage 4 :(

Sunnielee
29-09-14, 23:50
Mine only left the last 5% for carpark and drainage work before TOP, 2nd last 5% started from Apr...BLK22

DPan
30-09-14, 07:34
Mine only left the last 5% for carpark and drainage work before TOP, 2nd last 5% started from Apr...BLK22

Ya, me same. Left with last 5% before TOP.

v_esta
30-09-14, 12:01
Mine still stage 1.

-_-lll

CondoWE
30-09-14, 13:35
Mine is block 20 should be faster than all blocks but how come still at stage 2 nia?

i think It's time to call my lawyer to check it out....LoL!

1984
30-09-14, 17:04
Any others in blk 18?

DPan
30-09-14, 19:53
Mine is block 20 should be faster than all blocks but how come still at stage 2 nia?

i think It's time to call my lawyer to check it out....LoL!

Bro you really need to check cause i also block 20....

CondoWE
01-10-14, 12:30
Bro you really need to check cause i also block 20....

Yap, already asked my lawyer to write a letter to developer to check on it.

ahboy86
07-10-14, 21:12
Hi all. Been following this thread except my old account somehow got some problems so cannot post.

Glad to be back. Nice to meet all sea-esta owners.

haha. mine also only at 2nd loan dispersement only.

v_esta
07-10-14, 22:40
Yours is which block ah, ahboy86?

ahboy86
08-10-14, 08:17
Yours is which block ah, ahboy86?

am in 18 bro. u?

v_esta
08-10-14, 10:17
Blk 30... The slowest... :P

1984
08-10-14, 21:23
am in 18 bro. u?

Finally someone same blk as i am... lol

CondoWE
08-10-14, 22:06
Finally someone same blk as i am... lol

Beside ahboy86, still got 82 same block as you.......:tongue2: !

Block 18 ---> 84 units

Sat Han
09-10-14, 18:30
hi fri, I am also at block 18

v_esta
09-10-14, 21:13
Seems like there are quite many forumers who own a unit in Blk 18 worr.... :)

1984
10-10-14, 11:48
Seems like there are quite many forumers who own a unit in Blk 18 worr.... :)
Lol... glad to know there are many fellow blk 18 residents here... proabably may be on same level too...

ahboy86
10-10-14, 19:50
Finally someone same blk as i am... lol

haha nice to meet fellow block 18 residents, Sat Han and 1984; as well as all other residents in Sea Esta.

Sea Esta
10-10-14, 20:47
I am in blk 18 too.

ahboy86
13-10-14, 15:49
Dear friends. Wrote to developer not long ago. Just to share: 1)Completion of brick walls (5%) - 4th quarter 2014
2) Completion of ceiling (5%) - 4th quarter 2014
3) Completion upon door/window frames/electrical wiring/plumbing/internal plastering (5%) - 1st quarter 2015
4) Completion of carpark, roads and drains serving the project - 2nd quarter 2015
Please note the above date given is only estimation and we will not be liable for this estimation. We reserve the right to call for payment before or later than the above dates given.

v_esta
14-10-14, 07:43
Cool! Thanks for the info, bro!

But seems like most of the ceilings have been completed though.

v_esta
16-10-14, 16:14
Status update:

(1) Entrance seems to begin construction!!
(2) Part of Construction fences already taken down - suspect that they are starting to do the condo fences!
(3) Saw a block painted with mocca brown - nice!

CondoWE
17-10-14, 00:01
Status update:

(1) Entrance seems to begin construction!!
(2) Part of Construction fences already taken down - suspect that they are starting to do the condo fences!
(3) Saw a block painted with mocca brown - nice!

Yap..you are right...just visited yesterday saw the colour is white with mocca brown.

http://i1297.photobucket.com/albums/ag30/CondoWe/SE_15Oct14_zpsbbff952f.jpg (http://s1297.photobucket.com/user/CondoWe/media/SE_15Oct14_zpsbbff952f.jpg.html)

Sat Han
18-10-14, 10:43
dear all,

Normally, after roof top finished, 6 months to TOP for smooth projects.

v_esta
18-10-14, 13:29
That's great to hear!!

Seems like the ceilings all done already.
Meaning TOP coming soon!!??

Sea Esta
19-10-14, 17:10
Construction Progress - 19th October 2014

19th October 2014 - Close Up - All blocks completed and Sea Horizon EC is threatening to block the view.
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10666026_579568482149818_4793226089080109230_n.jpg?oh=64b83745c98afd0bcd48e1eea766e3ec&oe=54EBE841&__gda__=1420458283_0bf88eed80697014d45186e3633a7d0d

19th October 2014 - Panoramic View.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10520551_579568845483115_6913885254739257067_n.jpg?oh=3e54c1beff055be2a980be615acf0182&oe=54F2585B&__gda__=1425358819_4b24930b2219c9a6086b1bf2854ac177

19th October 2014 - Sea Esta from Pasir Ris Link.
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10501731_579568965483103_8484940063158341564_n.jpg?oh=0712220c0b433c43addab683852f4081&oe=54AE4ECA&__gda__=1420787011_993d7211db1e382733c5a8d915b2c14f

19th October 2014 - Block 18 is at Roof Level.
https://fbcdn-sphotos-a-a.akamaihd.net/hphotos-ak-xaf1/v/t1.0-9/10301289_579569048816428_2669760396242590322_n.jpg?oh=a7965c73069b5bdb39f71248934df16a&oe=54B47C54&__gda__=1424678373_fab3b296ab699021fdd76a4002cccfdb

19th October 2014 - Block 20 is at Roof Level.
https://scontent-a-kul.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10352906_579569188816414_4829093579427797811_n.jpg?oh=600d2abb66b5e9ecfb9cfa097af189fb&oe=54EE4DB0

19th October 2014 - Block 20 is at Roof Level. (Alternate View)
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10516838_579569272149739_4988557082656106608_n.jpg?oh=85e448445286b45819c6594353c32741&oe=54ECBB0E&__gda__=1420417234_3f87f3fd5b3b66c24468623b8a54c088

19th October 2014 - Block 22 is at Roof Level with new coat of paint.
https://scontent-b-kul.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10429240_579569375483062_1948421248427981086_n.jpg?oh=4dbcf4dc686312f48c557689accbe58a&oe=54EEC691

19th October 2014 - Block 22 is at Roof Level. (Alternate View)
https://scontent-b-kul.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/1554559_579569458816387_3983658050065144384_n.jpg?oh=bb3480b71b258212c3c869b5266bb320&oe=54E988C3

19th October 2014 - Block 26 is at Roof Level.
https://scontent-a-kul.xx.fbcdn.net/hphotos-xfa1/v/t1.0-9/1654268_579569685483031_1159526425452354152_n.jpg?oh=cfd7529178d6f70151b68812c7b78490&oe=54ABC6B2

19th October 2014 - Block 28 is at Roof Level with new coat of paint.
https://scontent-a-kul.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10420764_579569825483017_3134658829369782672_n.jpg?oh=6dae9dd5bcf202b264d7325fb308e2be&oe=54F6959A

19th October 2014 - Block 30 is at Roof Level.
https://scontent-a-kul.xx.fbcdn.net/hphotos-xfa1/v/t1.0-9/1924717_579569915483008_386195562002215232_n.jpg?oh=837576daeb6fb13f457b97919c25845c&oe=54F46706

19th October 2014 - Block 30 is at Roof Level. (Alternate View)
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/1017741_579570145482985_6704626732549229199_n.jpg?oh=b4ce6593769c8c318c21ddcbfe08fdc8&oe=54B325AF&__gda__=1420926098_28f6fac5621ec7c4d6390fe389cb5188

19th October 2014 - Block 24, the club house is completed.
https://scontent-b-kul.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10501696_579570242149642_1600751889676591580_n.jpg?oh=05f91cf6b59553dfa0d894c1d6d0e69c&oe=54F363B7

19th October 2014 - The guard room is in progress.
https://scontent-b-kul.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10698687_579570342149632_5190020856532994115_n.jpg?oh=d4e1a76e32f6a5be3ecbac11a9438b6c&oe=54B48AE3

19th October 2014 - Construction fence removed.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10376184_579570428816290_438041277702973782_n.jpg?oh=7057b3ed06214ab2bb943684cd6f622f&oe=54B7BB75&__gda__=1424906312_e3906d565f8e014f691e386b0b32a78f

19th October 2014 - Construction fence removed. (Alternate View)
https://scontent-b-kul.xx.fbcdn.net/hphotos-xfp1/v/t1.0-9/1798242_579570538816279_872765090654385231_n.jpg?oh=9c8bea2c803c054688260e540c12cc59&oe=54BC2DA4

v_esta
19-10-14, 22:31
Definitely looks like it's going to TOP soon! Haha

CondoWE
19-10-14, 22:35
Definitely looks like it's going to TOP soon! Haha

I am still struck at 45% nia so how to TOP soon.....:hopelessness:!

v_esta
20-10-14, 09:36
I'm lesser than you.. I still harboring the thought that it's going to TOP soon. Hahaha!

AG
20-10-14, 17:17
i am from block 22, i have paid 55%

081828
22-10-14, 22:38
I think they are working on the swimming pools. In one of the pics you can see the main drop off point is coming up.

v_esta
23-10-14, 07:46
Yup... think you are referring to the sunset Jacuzzi pool!!

Btw, which blk are you in? o_O

081828
23-10-14, 07:57
Yup... think you are referring to the sunset Jacuzzi pool!!

Btw, which blk are you in? o_O

I was referring to the main swimming pools (in the center). Are you able to tell from the 5th picture I've posted? I'm just making a guess here and I can't be sure. 

I also saw boxes labelled "teka" inside one of the low floor units.

v_esta
23-10-14, 21:26
The 5th picture is the sunset pool lor...

v_esta
23-10-14, 22:11
The 5th picture is the sunset pool lor...

081828
23-10-14, 23:52
The 5th picture is the sunset pool lor...

I took that pic between block 26 and 28 along JLB. Don't think is the sunset pool u r referring to, which is behind block 30 bah?

v_esta
24-10-14, 00:11
Oh.. paiseh. I thought you referring to the 6th photo. I am referring to the photo number 6. =P

radha08
27-10-14, 14:25
sea esta looking good...just passed by over the weekend....hope no delays like our good neighbours at seastrand...

v_esta
01-11-14, 14:40
Seems like both Seastrand and Watercolours are TOP-ing in Q4 of 2014........

Myeast
01-11-14, 14:50
Is there any chance Sea Esta can Top in Q1 2015 or early Q2 2015?? My neck is very very long la.......

v_esta
01-11-14, 15:21
Mine also! ^5

But I think they still doing the swimming pool and some units also not really completed. Probably Q2/2015? =D

DPan
01-11-14, 20:43
Is there any chance Sea Esta can Top in Q1 2015 or early Q2 2015?? My neck is very very long la.......

not likely, my estimate TOP for sea esta should be around Q3 2015

Sat Han
01-11-14, 22:31
:(, let hope for 2015 Q2.

v_esta
02-11-14, 16:55
Status update, again!

Just went to see our lovely home and saw that our fences is going to be partial concrete and partially metal. The metal part is based on my assumptions lah. I saw the concrete wall fences are up. Wonder how it's going to look like. Excited!

Yuki
02-11-14, 17:40
Wow the top date fast fast...

Btw anyone knows what's the things to expect nearer the top date? Like pay 6 months of maintenance fees or Simi survey fees? N how much?

Can also share the expected maintenance fee for the 2-bedders also? Am wondering how much...was reading in other threads it's something like $300++??

Lastly I was sharing this defect list n reno tips in the other thread which condo just TOP. Think you might find it useful too n start planning your reno.

http://diva79.blogspot.sg/2014/10/hdb-defect-checking-revisited.html

081828
03-11-14, 00:20
Status update, again!

Just went to see our lovely home and saw that our fences is going to be partial concrete and partially metal. The metal part is based on my assumptions lah. I saw the concrete wall fences are up. Wonder how it's going to look like. Excited!

Do you mean something like this? The area with the blue canvas backing...

https://farm8.staticflickr.com/7566/15507008508_4080e93953_c.jpg (https://www.flickr.com/photos/128833285@N03/15507008508/)
image (https://www.flickr.com/photos/128833285@N03/15507008508/) by 081828 (https://www.flickr.com/people/128833285@N03/), on Flickr

v_esta
03-11-14, 10:54
Umm.. not quite exactly what I meant. I was referring to the stretch of fence along Jalan Loyang Besar. Got chance I go back take photo. What I saw was full height concrete wall then empty space then full height concrete wall again, that Lind of pattern.

��

Myeast
04-11-14, 11:13
Thanks for update, went to exercise and pass by Sea Esta this morning, the fence is good, something like watercolor, but instead of 3 bars, it's a bigger solid wall, just wonder what color they will use...........Getting excited. Hope it will top in Q2....:)

081828
04-11-14, 22:58
Looking forward to picture updates from bro sea esta this weekend (hint hint) :hornybastard:

Good house
05-11-14, 15:21
Oh yes, I make detour to take a look, yes, brick wall...space...brick wall.....space......something nice and beautiful is coming

Sat Han
05-11-14, 19:24
Thanks for all the update, wanna go and see in some weekend.

Sea Esta
06-11-14, 01:52
Looking forward to picture updates from bro sea esta this weekend (hint hint) :hornybastard:

Will take some pictures of the fence this week to update all the Facebook fans n of course everyone in this forum. :D

Sea Esta
07-11-14, 22:20
Construction Progress - 7th November 2014 (Part 1)

7th November 2014 - Close Up - All blocks completed. The last crane at block 30 has been removed. PS: From the next update, we will stop taking pictures from this view as Sea Horizon EC is blocking the view.
https://scontent-a-nrt.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10173804_589772634462736_2423583926650895036_n.jpg?oh=5a4784764da92d3f89a05b056eeb4e85&oe=54D3EB07

7th November 2014 - Panoramic View. PS: From the next update, we will stop taking pictures from this view as Sea Horizon EC is blocking the view.
https://scontent-a-nrt.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/1932446_589772887796044_5858643841256891500_n.jpg?oh=2c594dbcb0de58360346c608ed67c232&oe=54F622FD

7th November 2014 - Sea Esta from Pasir Ris Link.
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/1236139_589773177796015_3191773080757565733_n.jpg?oh=83fe438d76ba84b738a2e20ca111877a&oe=54D4346A&__gda__=1423732395_79a1a6735b45c01b969d3be017f6ebe1

7th November 2014 - Block 18 is at Roof Level. (Road View Units)
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10295680_589773694462630_554423714423236827_n.jpg?oh=a05acf7121082163b3738454057b6e24&oe=54E95E6D&__gda__=1423868196_d8fe40a555df0665d5c627c6bbbc76d7

7th November 2014 - Block 20 is at Roof Level. (Road View Units)
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/1505061_589774057795927_4561915316373309456_n.jpg?oh=719a9dc320139a4a41b76cfbe8e7fe6c&oe=54EF2EED&__gda__=1424440438_bebb4cc5ec9ae8dc457cae5c9466840e

7th November 2014 - Block 22 is at Roof Level. (Sea View Units)
https://scontent-b-nrt.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/1969322_589774471129219_5523881247131328961_n.jpg?oh=d20a3e093a642370adedcecb12292c69&oe=54E259EC

7th November 2014 - Block 22 is at Roof Level. (Pool View Units)
https://scontent-a-nrt.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10613158_589775114462488_805706328800602333_n.jpg?oh=8b4a62f7e9d3b8ea3bab347c8e9fc68c&oe=54D55AB6

7th November 2014 - Block 26 is at Roof Level. (Sea View Units)
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10156049_589775691129097_9045182361359617534_n.jpg?oh=d8e5e24b78425356f381bc1c0ab61d98&oe=54E372FD&__gda__=1424304965_2da33d8538d13f4b37fb30e545e08932

7th November 2014 - Block 26 is at Roof Level. (Pool View Units)
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/1426357_589776397795693_14791185127438342_n.jpg?oh=7f03b7cf4908d17a8393176a48782c59&oe=54D2E336&__gda__=1424113483_b111a8405839fb3e5799293358a2f1d0

7th November 2014 - Block 28 is at Roof Level. (Sea View Units)
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10422272_589776637795669_8063128423290718771_n.jpg?oh=33a72d43dd93107935f5ea08eca8923e&oe=54DE2D7D&__gda__=1424458484_1552249030719361ad90c55ad991dc59

7th November 2014 - Block 28 is at Roof Level. (Pool View Units)
https://scontent-b-nrt.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/10636204_589777604462239_9026882030407977361_n.jpg?oh=c189cee1e5972fe121bebb418e72b42b&oe=54F4E762

7th November 2014 - Block 30 is at Roof Level. (Sea View Units)
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/1450865_589777861128880_6535775875914230008_n.jpg?oh=c57e99638904051339f35ebccea99cd5&oe=54DCF181&__gda__=1424684570_70b132320d2d5726f6ef65a1e76650b2

7th November 2014 - Block 30 is at Roof Level. (Road View Units)
https://scontent-b-nrt.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/553243_589778701128796_4804462448011291632_n.jpg?oh=04ac8cc917f96955848cf77880be8c57&oe=54DB6396

7th November 2014 - Guard House is in progress. (Front View)
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10407600_589779834462016_2929377825335090338_n.jpg?oh=9e29ca862449d8598220aabc6820c4a7&oe=54D82281&__gda__=1424526941_00c47eeba0a0a33f807fabb458ce2a6e

7th November 2014 - Guard House is in progress. (Right View)
https://scontent-b-nrt.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/11580_589780091128657_3304488518708178580_n.jpg?oh=c8318b434a3ad698ed39228d46dddbb2&oe=54DE3F1E

7th November 2014 - Guard House is in progress. (Left View)
https://fbcdn-sphotos-a-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10262034_589780571128609_8576305242258548572_n.jpg?oh=a531c2e429c89919bbfe37dfc46fabbd&oe=54F1A947&__gda__=1424588287_276bcdb9d3b8e59509c6d098ae865eff

7th November 2014 - Drop-off Point is in progress.
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/68192_589780874461912_5405716781840848972_n.jpg?oh=2c7e57715133fd749a0aaf1e6d739223&oe=54ED68AD&__gda__=1423964608_b12623dd800c00997b1e1897be113c3e

7th November 2014 - Drop-off Point is in progress. (Alternate View)
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10730844_589781534461846_1810279553144286137_n.jpg?oh=0d44378b340e627427435d3b49341f0c&oe=54E9930F&__gda__=1423508663_4456fc2278b301b6767a4c893945db2e

7th November 2014 - Staircase linking Drop-off Point to Block 18 is in progress.
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10526108_589781881128478_8546621179032969374_n.jpg?oh=7a4ea5e31eff413a4117eb7be5b5823c&oe=54E9E9E6&__gda__=1423231802_3d8246af6922fb2d3636945cdaa6378a

7th November 2014 - Electical Station is completed.
https://scontent-b-nrt.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/1982037_589782704461729_8937434872687821968_n.jpg?oh=1bd624178723de33921df7a179cc9d32&oe=54DC0AE1

Sea Esta
07-11-14, 22:23
Construction Progress - 7th November 2014 (Part 2)

7th November 2014 - Refuse collection point is completed.
https://scontent-a-nrt.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/13147_589783511128315_6110615735820439238_n.jpg?oh=1736e51f2f40bb825d1a54295d5b2aff&oe=54F1D058

7th November 2014 - Generator is installed. Not sure what is it for though.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10672440_589783044461695_1665401757752888282_n.jpg?oh=5b03221242ef5449b95933a0a7a241a8&oe=54E875C8&__gda__=1423371284_ea72e94109845fe9729082743f094ea7

7th November 2014 - Fence along Jalan Loyang Besar is in progress. Another step closer to TOP.
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/1466200_589784471128219_5528221711099304814_n.jpg?oh=185c5c0159213b61b129727987ff121e&oe=54F6C0C2&__gda__=1424544907_ecdc68a1b486f5196b5ea75882f43104

7th November 2014 - Fence along Jalan Loyang Besar is in progress. (Close Up View)
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xaf1/v/t1.0-9/1920102_589784904461509_3667464742087544491_n.jpg?oh=925898bd4b7be154a731258479a40eef&oe=54D92949&__gda__=1423387959_4fe29b7f806a5fb8326d2be7efaa3edc

7th November 2014 - Fence along Jalan Loyang Besar is in progress. (Alternate View)
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10530756_589785424461457_8438295345508245705_n.jpg?oh=0fbe38b6ca591ccfb066a941fbc08772&oe=551F1030&__gda__=1424981896_793690fedddd57a4691b4683d731c209

7th November 2014 - Fence along Jalan Loyang Besar is in progress. (Alternate View 2)
https://scontent-b-nrt.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/10392464_589785821128084_8142750103722192157_n.jpg?oh=9e09ee68da3a91c2ce38b338ef690c78&oe=54E99764

7th November 2014 - Fence at the junction of Pasir Ris and Paris Ris Link is in progress.
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10708_589786367794696_8483594516102061150_n.jpg?oh=ae9ebbaccfe3ac097b20d01d4f28f18d&oe=54DFEB17&__gda__=1423463956_a91df805f86c0b58752fb5e475c72c11

7th November 2014 - Sunset pool with jacuzzi seats is in progress.
https://scontent-b-nrt.xx.fbcdn.net/hphotos-xfa1/v/t1.0-9/10437737_589786814461318_3401804954100877101_n.jpg?oh=6ba9a0d46c370a75a74609ee3826ed8d&oe=54E54B0C

7th November 2014 - Gap between Block 28 and Block 30.
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/1908444_589787634461236_6366227349354119544_n.jpg?oh=6012a58238d67f3353294ac4241f0e02&oe=54D30CED&__gda__=1424238380_311eeac59a67b70444fa9c68b5442b27

7th November 2014 - Our neighbour condo, Watercolours fence. Our Sea Esta fence could be in similar design.
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10382653_589788294461170_8307420296862198187_n.jpg?oh=8d2ad13b32bcf9ab9fe64f955f8c1515&oe=54EEEABE&__gda__=1424925958_7c844b6939d12f263379a022f6dd1b81

v_esta
08-11-14, 08:20
Thanks for the plentiful photos, bro Sea Esta! Looking forward to TOP soon!

Sea Esta
08-11-14, 11:42
Thanks for the plentiful photos, bro Sea Esta! Looking forward to TOP soon!

No problem. Yes, hope can TOP in Q2 2015. :D

Sat Han
08-11-14, 15:30
Hi,

Can anyone advice, after TOP, how long have to wait to shift ?

AG
10-11-14, 10:57
Thanks buddy

v_esta
22-11-14, 19:59
Hi,

Can anyone advice, after TOP, how long have to wait to shift ?

I thought after TOP can straightaway stay if you don't do any reno?

v_esta
22-11-14, 20:00
Just passed by Sea Esta yesterday and seems like not much progress. Blk 30 still not complete. *sad siah*

081828
24-11-14, 01:40
Hi everyone, I took some pictures over the weekend and posted them on skyscrapercity forum:

http://www.skyscrapercity.com/showthread.php?p=119327672#post119327672

Enjoy!! :cheers3:

v_esta
24-11-14, 08:53
Wow. That's a lot of photos too. Thanks.

CondoWE
27-11-14, 19:23
Why block 30 so slow :sleep:?

Sat Han
28-11-14, 10:23
I tot , block 30 is start lately due to its access to center part.

Sea Esta
29-11-14, 23:13
Construction Progress - 29th November 2014 (Part 1)

29th November 2014 - Sea Esta from Pasir Ris Link.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10403304_599236460183020_7729773774932383533_n.jpg?oh=f576e64607826e936d5de19038822d75&oe=550ECE31&__gda__=1426692845_6b667c06c3b46728ca8d5649e671040e

29th November 2014 - Block 18 is at Roof Level. (Road View Units)
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10432539_599236633516336_8378778912005329848_n.jpg?oh=67d7ac1ec653af68c4c088c8bd028013&oe=55124D90&__gda__=1426552857_3da447fedbe20330d1114a21c60ff558

29th November 2014 - Block 18 is at Roof Level. (Upper Level, Pool View Units)
https://scontent-b-sin.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/10646628_599236776849655_7545328530594323678_n.jpg?oh=b214515cb9190dda579f235b290f2bcb&oe=5510B532

29th November 2014 - Block 20 is at Roof Level. (Road View Units)
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10383987_599236933516306_8052712628224012650_n.jpg?oh=941cecb7af6fcee672b49dee94055adf&oe=55069B9C&__gda__=1423528996_7069d19facc7adb8760682e4bdbd8b14

29th November 2014 - Block 20 is at Roof Level. (Pool View Units)
https://scontent-a-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10001388_599237070182959_2973499682624027569_n.jpg?oh=625614f3e6f729cbacb69977284ba932&oe=55168D79

29th November 2014 - Block 22 is at Roof Level. (Sea View Units)
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10505486_599237320182934_7676075585505433307_n.jpg?oh=51972af5571310731c0d9a532a7488e9&oe=5517D75D&__gda__=1426434433_93223c1ce92bc33afaf154e948128ab7

29th November 2014 - Block 22 is at Roof Level. (Pool View Units)
https://scontent-a-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10406466_599237640182902_3963767377520547640_n.jpg?oh=92700b3781b78ed72526efe08109fcee&oe=54D4BAFE

29th November 2014 - Block 26 is at Roof Level. (Sea View Units)
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/1499386_599237793516220_7589585029361193237_n.jpg?oh=9157ed629359e5787be30c3f427367a0&oe=55067F40&__gda__=1427652827_efa38773a39590ad885623cc9e8d0e6c

29th November 2014 - Block 26 is at Roof Level. (Pool View Units)
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10805813_599237966849536_7918884414565705539_n.jpg?oh=8e38239746c0b5fb76be968cdcc00fc5&oe=55087D38&__gda__=1427539940_d9b4761f57c2d08a2273d38f5fb7ea23

29th November 2014 - Block 26 is at Roof Level. (Ground Level, Sea View Units)
https://scontent-a-sin.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10690156_599238143516185_4883903504009160510_n.jpg?oh=b6272b4e57d91e774af6c8c28b45ff00&oe=5520400D

29th November 2014 - Block 26 is at Roof Level. (Ground Level, Sea View Units)
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/1513766_599238306849502_3096652024545974473_n.jpg?oh=effbb8cf9ebe9b73fe51236ffcc3af89&oe=551371E4&__gda__=1427801471_b3ce15635e9c72422775bb9b58a56a04

29th November 2014 - Block 28 is at Roof Level. (Sea View Units)
https://scontent-a-sin.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/10356770_599238436849489_2942519734056741618_n.jpg?oh=6e27aa2f334bcfdfd158008d18c8152d&oe=5516F33C

29th November 2014 - Block 28 is at Roof Level. (Pool View Units)
https://fbcdn-sphotos-a-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10389177_599238703516129_1643878295571176014_n.jpg?oh=e84547f04dfa071b8b1b3e4c50b21ea3&oe=54D6F59E&__gda__=1423112770_b641cca1de10426ac54a24e0ee268731

29th November 2014 - Block 28 is at Roof Level. (Ground Level, Sea View Units)
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10392336_599238953516104_1114767257232544006_n.jpg?oh=694b3c3ac60cc7d60a1ead99b527539c&oe=550F420D&__gda__=1423461223_d8138fa41ce511bba4e483137d567e33

29th November 2014 - Block 30 is at Roof Level. (Sea View Units)
https://scontent-b-sin.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10687178_599239270182739_1789978102727167301_n.jpg?oh=82adc6a5f708860e94398564de782262&oe=551C1862

29th November 2014 - Block 30 is at Roof Level. (Road View Units)
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10423873_599239476849385_1073239726039451331_n.jpg?oh=4670560289f8c289d0ad85fdef05c997&oe=551A62AE&__gda__=1427674226_69c773c6e81d884e8988d514e296dbaf

29th November 2014 - Club House is completed.
https://fbcdn-sphotos-a-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10689459_599239766849356_4579280644140746775_n.jpg?oh=22e4c5ada02de3c85927a109ab2d6840&oe=55130A14&__gda__=1427740332_79f5cb603de51343094c1ea966627659

29th November 2014 - Guard House is completed.
https://scontent-a-sin.xx.fbcdn.net/hphotos-xaf1/v/t1.0-9/10625011_599240100182656_2222442028922288795_n.jpg?oh=246ed095c25ac8fb622ef12dd41ec116&oe=550B9937

29th November 2014 - Fence along Jalan Loyang Besar is in progress.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/1896882_599240293515970_159679191345322260_n.jpg?oh=21e9ec19c057f2b6c320ee4ee1c285a2&oe=550DECAE&__gda__=1423505071_a16d617216576094f2ae30a5091cd2bd

29th November 2014 - Fence along Jalan Loyang Besar is in progress.
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10387393_599240473515952_156570015439364673_n.jpg?oh=9e8e92b656f19dd2712d6f7d0160ba45&oe=54D80624&__gda__=1426468377_f5df87529edb8503887191aa9ea4ead9

Sea Esta
29-11-14, 23:14
Construction Progress - 29th November 2014 (Part 2)

29th November 2014 - Fence along Paris Ris Link is in progress.
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10407473_599240646849268_4068364191245121250_n.jpg?oh=2247272b3f09c6c57f339bf595e94520&oe=551D26A2&__gda__=1426762440_f5a5a785f07ed242302acc5708ed8c42

29th November 2014 - Fence at the junction of Pasir Ris and Paris Ris Link is in progress.
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10445524_599240896849243_3840194769290106351_n.jpg?oh=2bd723715df6978cd2830dd00df0c72b&oe=551F50F6&__gda__=1426435228_6eb0b1f38a1c2989cdb82bc209d6594f

29th November 2014 - Sunset pool with jacuzzi seats is completed.
https://scontent-a-sin.xx.fbcdn.net/hphotos-xfa1/v/t1.0-9/1947380_599241070182559_4760318862318257636_n.jpg?oh=59cbadea89230ef945d42658597e4951&oe=54D61CED

29th November 2014 - Lanscaping near the Sunset Pool is completed.
https://scontent-a-sin.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/10441024_599241266849206_7150110182810858050_n.jpg?oh=32f417139b1f0468b89e349b6902321b&oe=5515587F

29th November 2014 - Sea Esta from Ripple Bay.
https://scontent-a-sin.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/1013639_599241476849185_5280926594324676909_n.jpg?oh=398ad8d81447555d21f884d61a0463ab&oe=54D4FF65

CondoWE
30-11-14, 10:12
Thanks bro Sea Esta for the pictures...:applouse:!

Sea Esta
02-12-14, 01:24
Thanks bro Sea Esta for the pictures...:applouse:!


You are welcome. :D

Sunnielee
03-12-14, 11:01
Hi Neighbors,

Just saw some photos taken by my friends for his EC unit @ Tampines whose developer and main contractor same as us. I got so worried about the quality work for our flats after reading through all those recording of hazard safety and poor quality works.

Like the rubbish chute is too small even without leg peddle. What is more, the chute door opens to lift lobby and just beside the lift door!!!
There are sharp edge in swimming pool, narrow pavement, water ponding in letter box when rains, narrow driveways, no sheltered linked way...

Not to mention the interior works.. oh My

v_esta
03-12-14, 23:25
Ummm, bro. But you comparing an EC with a Private Condo leh. Not relative comparison leh. The quality of the materials used for both projects are different also.

DPan
04-12-14, 06:30
Ummm, bro. But you comparing an EC with a Private Condo leh. Not relative comparison leh. The quality of the materials used for both projects are different also.

Agree, let hope all will be swee swee

CondoWE
10-12-14, 11:00
My bank released another 10% to developer liao... now become 55%..hehe:cheers4:!

Sat Han
10-12-14, 13:48
How u check bro! I am not familiar with those things!

v_esta
10-12-14, 14:22
You'll receive a letter from your lawyer to inform you about this.

CondoWE
10-12-14, 19:41
You'll receive a letter from your lawyer to inform you about this.
He don't....b'cos show hand liao...haha..just joking...lol.

Yap..recieved letter from lawyer few weeks ago.

v_esta
10-12-14, 22:00
Walao, gave me a scare... I thought show what hand... Haha... I think Sat Han is block 30? So won't get the letter for next payment yet? Since block 30 is the slowest. Haven't complete also. -_-!!!

Sat Han
11-12-14, 07:19
Bro! I am at block 18.

v_esta
11-12-14, 08:01
Oops. That means same as bro Sea Esta! Hehe

AG
11-12-14, 14:48
mine is already 55% two months back. i am from blk 22

Sea Esta
11-12-14, 22:08
Oops. That means same as bro Sea Esta! Hehe

Yup. Me blk 18. :D

CondoWE
14-12-14, 11:01
mine is already 55% two months back. i am from blk 22

Your unit is ground, low, mid or high floor?

My lawyer wrote to the developer and was told that ground floor will be slower when come to internal work like ceiling, glass door to patio...:blue:!

Sea Esta
21-12-14, 19:31
Construction Progress - 21st December 2014 (Part 1)

21st December 2014 - Sea Esta from Pasir Ris Link.
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10882094_608199495953383_7509412260449281786_n.jpg?oh=31fe88a149fa93df4ed98e133d45bf68&oe=55420074&__gda__=1426478845_0c36806a3194b637c18120dd08b0cfff

21st December 2014 - Block 18 is at Roof Level. (Road View Units)
https://scontent-b-nrt.xx.fbcdn.net/hphotos-xpf1/v/l/t1.0-9/10428006_608199619286704_8441415754779737848_n.jpg?oh=42092f9926b8f84494cb2ea6445e11a9&oe=5504915E

21st December 2014 - Block 20 is at Roof Level. (Road View Units)
https://scontent-b-nrt.xx.fbcdn.net/hphotos-xfp1/v/t1.0-9/1982297_608199762620023_7472514994776358227_n.jpg?oh=00f3f4284c8b08cef029249ab2345cac&oe=54FB7E33

21st December 2014 - Block 20 is at Roof Level. (Pool View Units)
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xfa1/v/t1.0-9/10806228_608199962620003_1340064529435599063_n.jpg?oh=8d0f04198933523bce958364dcc62f55&oe=55350CD3&__gda__=1426537957_41224079ce79cbc9631fb82b51ce5b1e

21st December 2014 - Block 22 is at Roof Level. (Sea View Units)
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xfa1/v/t1.0-9/10415551_608200109286655_2630665731918500342_n.jpg?oh=8e5e0c7a2deef02bd709c15dc65ead73&oe=554088B5&__gda__=1425956739_16cd0399f4531269493b7b51d76fb700

21st December 2014 - Block 22 is at Roof Level. (Pool View Units)
https://fbcdn-sphotos-a-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10422478_608200229286643_2219192206190132307_n.jpg?oh=aaef78ce7d4d29df4d155d0df926b4ea&oe=55468FF5&__gda__=1426597965_9759721c829ae48e2dc995f21bcd1ec9

21st December 2014 - Block 26 is at Roof Level. (Sea View Units)
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xfa1/v/t1.0-9/10384452_608200399286626_7048389086147704452_n.jpg?oh=f527fdf960929eb801d2b9ecef6eb169&oe=55355B72&__gda__=1429861956_01bfe7ece4abf31ffb94d47a3fea4561

21st December 2014 - Block 26 is at Roof Level. (Pool View Units)
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10367572_608200542619945_7025406881567667357_n.jpg?oh=e6e9d267aaf2e9137d17420b1cf9b663&oe=54FD6CEA&__gda__=1429564544_812bd2e97de10e0b7d3a7e107026683b

21st December 2014 - Block 28 is at Roof Level. (Sea View Units)
https://scontent-b-nrt.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10802043_608200659286600_3879165873108973995_n.jpg?oh=c49729273cef6a17776c0e6d7bb7cdc1&oe=554554B4

21st December 2014 - Block 28 is at Roof Level. (Pool View Units)
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/1450299_608200855953247_2536750508821651505_n.jpg?oh=c35bb5263344eccfc34dc933b6faf96b&oe=553B6F18&__gda__=1430170705_6db2f9f8c7128e54c941d8c35878801c

21st December 2014 - Block 30 is at Roof Level. (Sea View Units)
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10858419_608201149286551_8638810783771805133_n.jpg?oh=17e3651c9a00e9977e1c8e6ea9b91742&oe=55461A2E&__gda__=1429585302_da6c26247c8cc6364aef02e2b1a18af3

21st December 2014 - Block 30 is at Roof Level. (Road View Units)
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10500587_608201005953232_6351010006469619727_n.jpg?oh=2b3c556b2f7036d19e1d7e58956c9b08&oe=55371D21&__gda__=1430721355_027f1e8af62e1494c4e2b75d484b960a

21st December 2014 - Block 24 (Club House) is completed.
https://scontent-a-nrt.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/1656260_608201819286484_23833077244314940_n.jpg?oh=b87bc92627f66d2f1cc9112bd6a5de29&oe=553592CE

21st December 2014 - Worker Quarter is being removed. Tennis Court will be build at the site.
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/16811_608202012619798_4860090924831065020_n.jpg?oh=58f8ef448c493100758437b5321afbb2&oe=553618CC&__gda__=1430699471_a97075d6b7b014fbbdf6e2543b949929

21st December 2014 - Fence along Jalan Loyang Besar is in progress.
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/14293_608202829286383_3392608476117264156_n.jpg?oh=534ea4f9373df2c44a0cde0cf579e934&oe=54FA2234&__gda__=1426713161_541bfa4d14f449cae7aa764e423bb5f5

21st December 2014 - Fence along Jalan Loyang Besar is in progress.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10857751_608202982619701_569346654183582125_n.jpg?oh=90ccf34175fec7f09306b106edc2f81c&oe=55377B77&__gda__=1426616502_a15173a152a488eb573c879a65569b8d

21st December 2014 - Fence along Jalan Loyang Besar is in progress.
https://scontent-a-nrt.xx.fbcdn.net/hphotos-xfa1/v/t1.0-9/10455153_608203099286356_1268716874656579334_n.jpg?oh=2164ecdbf2f378755b9cda5594849e21&oe=553CE7A0

21st December 2014 - Fence at the junction of Pasir Ris and Paris Ris Link is in progress.
https://scontent-a-nrt.xx.fbcdn.net/hphotos-xfa1/v/t1.0-9/10406910_608203339286332_143441965367441199_n.jpg?oh=133798f5066018377641befe6d2b7f39&oe=553582BD

21st December 2014 - Fence at the junction of Pasir Ris and Paris Ris Link is in progress.
https://scontent-a-nrt.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10850295_608203552619644_7606845362922945614_n.jpg?oh=ee0cb6fa2ed989f5b5be275d29b57c02&oe=5504FFF2

21st December 2014 - Sunset pool with jacuzzi seats is completed.
https://scontent-a-nrt.xx.fbcdn.net/hphotos-xaf1/v/t1.0-9/1966740_608203719286294_549387827972919642_n.jpg?oh=05d39fc0eda07c9003cab598d893bbbe&oe=5502A9D3

Sea Esta
21-12-14, 19:32
Construction Progress - 21st December 2014 (Part 2)

21st December 2014 - Lanscaping near the Sunset Pool is completed.
https://scontent-b-nrt.xx.fbcdn.net/hphotos-xaf1/v/t1.0-9/10365855_608202345953098_5772088799362318885_n.jpg?oh=4e40a9a3dfbadadf04de8d6d3b22b329&oe=5545D060

21st December 2014 - Our neighbour, Water Colours, sign is up.
https://scontent-b-nrt.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10858625_608203902619609_1435834940628436955_n.jpg?oh=551bb25fd601f14743068b870af4a817&oe=553EB621

Good house
21-12-14, 22:47
Hi bro, thank you for the very nice picture.

DMCK
22-12-14, 10:24
at least the surrounding fence is not those metal industrial type like the neighbour condo..

v_esta
25-12-14, 01:50
On the fence, it looks like they are trying to make it look consistent by having the same type of grills as the balconies. :)

1984
25-12-14, 14:52
Merry Christmas everyone!!!

Received another letter from the lawyer for payment... now blk 18 at stage 5 of 7! :joyous::joyous::joyous:

081828
27-12-14, 22:04
Took some pictures on 14 Dec 2014 and posted them on skyscrapercity forum. Sorry folks, couldn't find the time to post till now....

http://www.skyscrapercity.com/showpost.php?p=120199190&postcount=29

081828
27-12-14, 22:19
Took some pictures on 14 Dec 2014 and posted them on skyscrapercity forum. Sorry folks, couldn't find the time to post till now....

http://www.skyscrapercity.com/showpost.php?p=120199190&postcount=29


http://www.skyscrapercity.com/showpost.php?p=120199480&postcount=30

v_esta
29-12-14, 22:15
OMG! You went into Sea Esta?!

BOB
04-01-15, 17:27
Was at Sea Esta today. Stood right outside Stack/Blk 20, could see through the glass windows of master bedroom of 3rd floor unit. The room's aircon have been installed and the built-in wardrobe were done. Room painted white.

CondoWE
04-01-15, 21:36
http://www.skyscrapercity.com/showpost.php?p=120199480&postcount=30

Post #30, balcony grille painted dark green?

1984
05-01-15, 14:26
Nah, think there was a coating on it when the picture was taken. I went yesterday and they are all silver.

Sea Esta
10-01-15, 23:32
Construction Progress - 10th January 2015 (Part 1)

10th January 2015 - Sea Esta from Pasir Ris Link.
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10933814_619517808154885_2821921946722446981_n.jpg?oh=0f761d0cfdf14ad16a1ebc0eeb17b3de&oe=5526EDAB&__gda__=1430173377_c48ea3007fc782db8ea1b37fcc82481f

10th January 2015 - Block 18 (Road View Units).
https://scontent-a-sin.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/1524743_619518294821503_5235976326205009633_n.jpg?oh=dba49e50468fda63241f3a7405dce91c&oe=553DE498

10th January 2015 - Block 18 (Pool View Units).
https://scontent-a-sin.xx.fbcdn.net/hphotos-xaf1/v/t1.0-9/10427310_619518604821472_3856172662611995156_n.jpg?oh=360d222b0ca288d4e979b56e0b663878&oe=556C1C82

10th January 2015 - Block 20 (Road View Units).
https://scontent-a-sin.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10013920_619519074821425_2323048527262232453_n.jpg?oh=22f942d47c109216e41dfb3cdf0f372a&oe=55682418

10th January 2015 - Block 20 (Pool View Units).
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10915138_619519198154746_7951871101390754831_n.jpg?oh=ba8d15598bd28293e63799e4e6dc347b&oe=55347CDD&__gda__=1433366885_ff05c3ac3b0da755e4e0bd5e0261f343

10th January 2015 - Block 22 (Sea View Units).
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10915138_619519198154746_7951871101390754831_n.jpg?oh=ba8d15598bd28293e63799e4e6dc347b&oe=55347CDD&__gda__=1433366885_ff05c3ac3b0da755e4e0bd5e0261f343

10th January 2015 - Block 22 (Pool View Units).
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10906152_619519948154671_8747622069117088899_n.jpg?oh=55bfaaee671b57732063b3e1998a0f2d&oe=552BA560&__gda__=1428267964_fa18e30b3f01f433ed8f2830503d0365

10th January 2015 - Block 26 (Sea View Units).
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10882217_619520168154649_6138409082275309898_n.jpg?oh=e2041792974d5fcab3235432091691a3&oe=55257FAD&__gda__=1428347505_d382a680b58d22ce7a5002c242267db1

10th January 2015 - Block 26 (Pool View Units).
https://scontent-b-sin.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/10712983_619520358154630_6083271167547613385_n.jpg?oh=9185941ed7eb664db454e3d420621b24&oe=553BE9B5

10th January 2015 - Block 28 (Sea View Units).
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xfa1/v/t1.0-9/10922494_619520611487938_8998435163440237173_n.jpg?oh=905ede0435d17469cc874c99dbe6e1bc&oe=55691BA3&__gda__=1428924053_c6f63acf87b32c8beaee6ce5e66e6384

10th January 2015 - Block 28 (Pool View Units).
https://scontent-a-sin.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/10922627_619520814821251_2290711948158764048_n.jpg?oh=56ccfc5d0a4e280bfdb303c133c88698&oe=5525ABFA

10th January 2015 - Block 30 (Sea View Units).
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10917826_619521084821224_5069817126616416126_n.jpg?oh=c54d45fd5e7d9cf3c9eedb8cb4a6c45a&oe=5532ADA6&__gda__=1428872058_ecc151ff246c6b5ea8f345d5712d951c

10th January 2015 - Block 30 (Road View Units).
https://scontent-b-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10422364_619521251487874_7617382509279267507_n.jpg?oh=e1feb43fce4ed0167a742fe5f3f4f05f&oe=5529A8BB

10th January 2015 - Block 24 (Club House).
https://scontent-b-sin.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10898231_619521874821145_3502829904058877736_n.jpg?oh=fdafbc05cc8e709a74bd7642970e0ee9&oe=553E427A

10th January 2015 - Guard House.
https://scontent-b-sin.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/1978861_619521658154500_7194632864838937947_n.jpg?oh=25c973454a414f7725128539aa382de0&oe=5538E31C

10th January 2015 - Worker Quarter has beemn removed. Tennis Court will be build at the site.
https://scontent-a-sin.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10928185_619522398154426_6379551909858554562_n.jpg?oh=e11fb24e0b32d202d73dee1abf235f18&oe=553F754A

10th January 2015 - Fence separating Sea Esta with Ripple Bay.
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xaf1/v/t1.0-9/10924779_619522991487700_5225733143625314958_n.jpg?oh=d556fb4eb13ad3ebc3facad9f53ff4c4&oe=556E32C1&__gda__=1428487536_82f5febc72249f9bc7c1fc360ece6455

10th January 2015 - Fence along Jalan Loyang Besar.
https://scontent-a-sin.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10926384_619523201487679_5304496206874437198_n.jpg?oh=e8a97a039a1100b2725bf40ac3f52272&oe=553CDA81

10th January 2015 - Fence along Jalan Loyang Besar.
https://scontent-a-sin.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/10906538_619523464820986_4042930544176896430_n.jpg?oh=1a761f508873efa9306c8aed81c4af7f&oe=55367360

10th January 2015 - Ground unit of Blk 26.
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10898328_619523778154288_3657749875915126120_n.jpg?oh=5cc5d3aa792f8af88013728c2cc61387&oe=5535404D&__gda__=1429994641_cf7c24ba985643e2e7c8dac291db6c65

Sea Esta
10-01-15, 23:33
Construction Progress - 10th January 2015 (Part 2)

10th January 2015 - Ground unit of Blk 26.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10392472_619523988154267_6243580353638510249_n.jpg?oh=755ce1580b952b216b27059e19fcd0d1&oe=556D95E4&__gda__=1433140316_99de940bce9ed780e76dc5b48493cdc3

10th January 2015 - Landscaping.
https://fbcdn-sphotos-a-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10698407_619524321487567_8108922338254798097_n.jpg?oh=f828691089862143ee042d88a75b1379&oe=552C4369&__gda__=1433107971_41f18773b1fbe3971b007aedb1593e41

10th January 2015 - Landscaping.
https://scontent-a-sin.xx.fbcdn.net/hphotos-xfa1/v/t1.0-9/10926384_619524491487550_8370382553654750126_n.jpg?oh=4fa90d2ea0197ecb86b040bfcc0bf242&oe=5535A436

10th January 2015 - Landscaping.
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10933920_619525044820828_3239399803361205701_n.jpg?oh=7780b029fc03a6da6e1810aee2ccdd26&oe=5535A2CF&__gda__=1433237623_4c12b245b988512e98c39d350001182b

10th January 2015 - Sunset pool with jacuzzi seats.
https://scontent-a-sin.xx.fbcdn.net/hphotos-xap1/v/l/t1.0-9/10898199_619525208154145_282037547036671214_n.jpg?oh=920cadec9dfbe217c8da9f92558ec048&oe=55402C06

10th January 2015 - Sea Esta From Pasir Ris Car Park A.
https://scontent-b-sin.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/10926466_619525804820752_8144704406472957475_n.jpg?oh=abf10445dd1e5c887c7491bff9ab4451&oe=553BE8B4

10th January 2015 - Seastrand vs Water Colours signage.
https://scontent-b-sin.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10906569_619526101487389_1880610531337437057_n.jpg?oh=182b770fbdf9ca7f4a16a97fbdd24a4e&oe=55398AA8

10th January 2015 - The big 4.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10922624_619526308154035_6974318185798016069_n.jpg?oh=dddbe62a82b842672c52a7fa59933a35&oe=556C34E2&__gda__=1433026394_a0b5cf9997addc037b0b779536bf9938

CondoWE
11-01-15, 09:44
Thanks for the 2015 update...:im-so-happy: :im-so-happy: :im-so-happy:!

Btw, what is the purpose of the roof top circled in red? Wouldn't the holes can green algae easily exposing under sun and rain ?

http://i1297.photobucket.com/albums/ag30/CondoWe/Top_zps257bc6b9.jpg (http://s1297.photobucket.com/user/CondoWe/media/Top_zps257bc6b9.jpg.html)

Sat Han
11-01-15, 10:57
The ledge is shutter for escape stair storey shutter under SCDF regulation code. Look like there was poor coordination between contractors and consultant. Any way, look ok!

acosean
11-01-15, 11:42
The BIG FOUR are indeed up and coming! Dunno when the bistro n convenient store of seastrand be ready.

CondoWE
11-01-15, 17:12
The ledge is shutter for escape stair storey shutter under SCDF regulation code. Look like there was poor coordination between contractors and consultant. Any way, look ok!

Just curious, why not all units have it since it's under SCDF regulation code leh :confusion:?

Sat Han
11-01-15, 18:09
Code say There should cover with RC around escape stair ( forgot how far offset), that is why a lot RC ledge at all condo unit. Near escape stair unit more chance to have ledge.
Also can not cover full RC, if full RC slab, URA is count as GFA. Than, they do RC grill.
This 1st storey is higher floor to floor height,
So much have more covered RC.

081828
11-01-15, 19:51
Do u guys think sea esta will top by end march 2015?

CondoWE
11-01-15, 20:08
Do u guys think sea esta will top by end march 2015?

Unlikely. June-July higher chance :jump-for-joy:!

DPan
11-01-15, 20:30
Unlikely. June-July higher chance :jump-for-joy:!

Yes, just like what i have predicted - quarter 3 2015

v_esta
11-01-15, 23:08
Wow... bro Sea Esta photos are really detailed!

Everything looks good. Hopefully internal is the same as well!

CondoWE
17-01-15, 21:28
Pasir Ris Park panorama view.

http://i1297.photobucket.com/albums/ag30/CondoWe/panoramaview_zps20a47717.jpg (http://s1297.photobucket.com/user/CondoWe/media/panoramaview_zps20a47717.jpg.html)

http://i1297.photobucket.com/albums/ag30/CondoWe/DSC_0545_zpsc1246d56.jpg (http://s1297.photobucket.com/user/CondoWe/media/DSC_0545_zpsc1246d56.jpg.html)

Allthepies
17-01-15, 21:31
Nice : )

v_esta
18-01-15, 09:01
Nice blue skies and beautiful greenery... ��

CondoWE
18-01-15, 12:12
From the picture, I guess the red pointer area is to build the entrance to basement carpark as the other side of the wall is quite near to the blk 18, unit 07 and 06 . What do you guy think?

http://i1297.photobucket.com/albums/ag30/CondoWe/CARPARKENTRANCE_zps22e7129c.jpg (http://s1297.photobucket.com/user/CondoWe/media/CARPARKENTRANCE_zps22e7129c.jpg.html)

Mickey Mouse
18-01-15, 12:56
Hi folks. Not sure if you feel the same but I find that the exterior design of condo buildings these days looks like HDB flats... some more build so closely to one another as well... unlike the old condos of yesterday.. :(:(:(

Anyone shares the same thoughts?

CondoWE
18-01-15, 18:23
Hi folks. Not sure if you feel the same but I find that the exterior design of condo buildings these days looks like HDB flats... some more build so closely to one another as well... unlike the old condos of yesterday.. :(:(:(

Anyone shares the same thoughts?

The other way round....HDB standard improving and outlook following private condo... :highly_amused:! !!

Btw due to land cost increase, all new houses be it private, landed or public, the floor area is getting smaller and expensive compare to old condo...:gun3:.

Sea Esta
01-02-15, 04:44
Construction Progress - 31st January 2015 (Part 1)

31st January 2015 - Sea Esta from Pasir Ris Link.
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10917860_628067387299927_91162474512344844_n.jpg?oh=3dbcf06e4c4cc70afacf1e35bea52ec5&oe=554F6518&__gda__=1428234394_c52e99adb2847433ad78128f66d37234

31st January 2015 - Block 18 (Road View Units).
https://scontent-a-sin.xx.fbcdn.net/hphotos-xfp1/v/l/t1.0-9/10394862_628068537299812_7001738337128580879_n.jpg?oh=b9925e5f164548e30060d0aad9f9e3d7&oe=556DE93C

31st January 2015 - Block 18 (Pool View Units).
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/1898098_628069047299761_2651866825887976494_n.jpg?oh=accd491340005c4a11ee85cba16bfab4&oe=55537C97&__gda__=1431518294_145026edb60e1985428c15c139a2e6b4

31st January 2015 - Block 20 (Road View Units).
https://scontent-a-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/1507985_628069680633031_3595562397140620432_n.jpg?oh=4ac8c4fa8ecf39b8cabd05c4d058056c&oe=5555D4DC

31st January 2015 - Block 20 (Pool View Units).
https://fbcdn-sphotos-a-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10968455_628070350632964_5300727758012135018_n.jpg?oh=3d39d81d388364d4c7c1fb3c0ca53a22&oe=5559A43E&__gda__=1431528582_0eede4cb9926e1b2fe61bf268a2dc508

31st January 2015 - Block 22 (Sea View Units).
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/522148_628070473966285_3328026372910029284_n.jpg?oh=4823ec423110414c604d11045dd63933&oe=55607F0C&__gda__=1431609056_f50724df2e87c11763469478f7520c2a

31st January 2015 - Block 22 (Pool View Units).
https://scontent-a-sin.xx.fbcdn.net/hphotos-xfp1/v/t1.0-9/10942493_628070610632938_5543475314684496451_n.jpg?oh=8aa8ff40f9a6d423fbbaa40b7c00dfa1&oe=5556FA0C

31st January 2015 - Block 26 (Sea View Units).
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10945599_628070763966256_3263268205199990850_n.jpg?oh=d3e81c6c1294191c5e9fc3a52ca6e2e9&oe=5557075C&__gda__=1433086933_7742dc1caf5a035b7aef3d3b97a75c33

31st January 2015 - Block 26 (Pool View Units).
https://scontent-b-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10959322_628070863966246_555624867655883217_n.jpg?oh=0f218d0e22ed91946f7ae512a700da26&oe=5568A92C

31st January 2015 - Block 28 (Sea View Units).
https://scontent-b-sin.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/10470607_628070960632903_217765272061966302_n.jpg?oh=99bbcca71caf4df27a811d6e56b4f099&oe=556AEAB7

31st January 2015 - Block 28 (Pool View Units).
https://scontent-b-sin.xx.fbcdn.net/hphotos-xfp1/v/t1.0-9/10393751_628071100632889_651848244939682910_n.jpg?oh=b8d22bf6bbc2ebefabf8a4ccf372dc56&oe=556D4C16

31st January 2015 - Block 30 (Sea View Units).
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/1385464_628071213966211_2977336550566201463_n.jpg?oh=7916529e5a145f0e262c83a5e8e93a98&oe=552325C3&__gda__=1432598782_d5677c34bc00a5b48589ec941f733af9

31st January 2015 - Block 30 (Road View Units).
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/1487377_628071473966185_6824514538567220120_n.jpg?oh=73bae3a35f32a0d4b2136bf7ad104ee9&oe=55526996&__gda__=1431401997_5ba10631e4fdf366918e392224e18385

31st January 2015 - Block 24 (Club House).
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10394814_628071617299504_4285355263406975641_n.jpg?oh=742a1ff094b44aa70c64c1295924c5e6&oe=55604317&__gda__=1432391371_bde286db1a4bf23b9280ce0e7a9dcad3

31st January 2015 - Block 18 and 20.
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xaf1/v/t1.0-9/10524322_628072210632778_8111107523810341502_n.jpg?oh=751b756635d6da8228274ce5438f854d&oe=556E6104&__gda__=1433325749_bcb5f2ec90e66a0ab4ce01ce03b65a38

31st January 2015 - The gap between block 18 and 20 with block 26 at the back.
https://scontent-b-sin.xx.fbcdn.net/hphotos-xfp1/v/t1.0-9/1486784_628072820632717_8158353864509878764_n.jpg?oh=deae97fa3e3c468edcf8ce3982db2bda&oe=55524353

31st January 2015 - Ground unit of block 26.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10171178_628072937299372_6184637772185560784_n.jpg?oh=942d4d0c7c6669108a039e14160bdae6&oe=555340E8&__gda__=1432562818_a0ddd8718547559822b4c4bc8ec30381

31st January 2015 - The signage of Sea Esta will be eventually located here at the main entrance.
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10806288_628073133966019_2099097552118944169_n.jpg?oh=6d92efad4f26f94d336090edcaa49ad5&oe=556307EF&__gda__=1432044631_6c911cad3765c6cfa9309eba6fa81055

31st January 2015 - The pavilion near the tennis court.
https://scontent-a-sin.xx.fbcdn.net/hphotos-xfp1/v/t1.0-9/10945651_628073367299329_2219998409800160031_n.jpg?oh=5723184ff4320c12822211ec89bf6fea&oe=556C4480

31st January 2015 - The under ground car park entrance.
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10557431_628074343965898_517946937604540096_n.jpg?oh=b2de7ead4b4831b5e48b7e42324665e1&oe=55579C9B&__gda__=1431341914_94594adf2e93c043d9a8e0ac6ea96b8d

Sea Esta
01-02-15, 04:45
Construction Progress - 31st January 2015 (Part 2)

31st January 2015 - The main drop-off area and the stairs leading to Block 18.
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10958327_628074780632521_8880202193575956794_n.jpg?oh=0c3dc8fd27f6480562685457c6f564cd&oe=5552BA5D&__gda__=1433022932_97ff3fa9691ce16c3373dd626f8ee110

31st January 2015 - The place where the adventure playground will be located.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/13699_628074940632505_1055037609920694654_n.jpg?oh=cb00a08b89406d0b4dcd47fa37289278&oe=55690407&__gda__=1432982634_eceeb95415de78f7b3a398579ea4be2b

31st January 2015 - Fence at the junction of Pasir Ris Link and Pasir Ris Rise.
https://scontent-b-sin.xx.fbcdn.net/hphotos-xfp1/v/t1.0-9/960287_628075107299155_8539457076061389833_n.jpg?oh=561e0c79e46f58763d60e4df56491bac&oe=55531D52

31st January 2015 - Fence along Jalan Loyang Besar.
https://scontent-a-sin.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10882249_628075343965798_4760719023921950882_n.jpg?oh=52748bc4170450c810945f3768ced753&oe=55217E8C

31st January 2015 - Fence along Jalan Loyang Besar without painting.
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xaf1/v/t1.0-9/10406359_628075460632453_5427998069742317109_n.jpg?oh=5de06d99b11cd38702ab5b00c06c936f&oe=554F1C0C&__gda__=1433328061_22a60182bad1090c06ce024e4337d6d4

31st January 2015 - Fence along Jalan Loyang Besar with painting.
https://scontent-a-sin.xx.fbcdn.net/hphotos-xaf1/v/t1.0-9/10846119_628075713965761_3913206960601048706_n.jpg?oh=5ff805f2055a536a13321c8300c9c556&oe=5569648A

31st January 2015 - Fence along Pasir Ris Link.
https://scontent-a-sin.xx.fbcdn.net/hphotos-xfa1/v/t1.0-9/11722_628075947299071_4542773203157620417_n.jpg?oh=9d69d2daf7a2f51decd69873f8cffb39&oe=556AA42A

31st January 2015 - The remaining part of Pasir Ris Rise is opened.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10958075_628076150632384_9140437809064163145_n.jpg?oh=7b55a6db23aa9c66761c2edc676adc3d&oe=556A8B38&__gda__=1431466929_99d740cbf16143881975ad3a8847b276

v_esta
01-02-15, 06:51
Really nice!

I was quite pleasantly surprised by the outcome of the design of our fences. :)

Myeast
01-02-15, 21:12
Thanks a lot for the nice photos update, I like the design of the fence too, hope Sea Esta can top earlier, not till the school exam time.......:drinking_coffee_ico

Just wonder, Will it be too early to find ID or contactor after CNY?

CondoWE
02-02-15, 15:04
Thanks a lot for the nice photos update, I like the design of the fence too, hope Sea Esta can top earlier, not till the school exam time.......:drinking_coffee_ico

Just wonder, Will it be too early to find ID or contactor after CNY?

haha..I won't do it until I see my actual unit :hornybastard:!

v_esta
03-02-15, 21:14
Yah! Too early!

Don't even have the actual floor plan yet!

CondoWE
06-02-15, 06:42
Does anyone know the washing machine given is top or front loading and what brand is it :drinking_coffee_ico ?

v_esta
06-02-15, 08:09
I remember it should be front loading.

The brand to be confirmed.

CondoWE
06-02-15, 18:53
I remember it should be front loading.

The brand to be confirmed.

Good if front loading. The WM under the table top will have more table space in the kitchen...:kiwi-fruit:.

v_esta
08-02-15, 17:37
Good if front loading. The WM under the table top will have more table space in the kitchen...:kiwi-fruit:.

But I think hor, above the washing machine, there's going to be a dryer.

CondoWE
08-02-15, 17:50
But I think hor, above the washing machine, there's going to be a dryer.

Got dryer meh? I thought only free fridge and washing machine nia....:courage:!

DPan
08-02-15, 22:28
Got dryer meh? I thought only free fridge and washing machine nia....:courage:!

Have, use own $$ buy.....

CondoWE
09-02-15, 14:24
Have, use own $$ buy.....

haha...I dun like to use dryer leh...if free than I'm ok :glee: !

CondoWE
09-02-15, 14:36
Does anyone happen to know whether the bedroom built-in wardrobe come with swing door or sliding door?

DPan
09-02-15, 16:17
Does anyone happen to know whether the bedroom built-in wardrobe come with swing door or sliding door?

If remember correctly should be swing door on display in showflat

v_esta
14-02-15, 15:31
Wow!

It's really beautiful!

9938

9939

9940

CondoWE
18-02-15, 08:51
Wishing SEA ESTA owner a prosperous and joyful GOAT year ahead!

新年快乐!年年有鱼!

羊羊得意過肥年....:victorious:!

DPan
18-02-15, 09:16
Wishing All Sea Esta owner
住洋房
喝洋酒
发发发啊

1984
18-02-15, 10:07
In front of block 18 there is a metal structure they are building at the site which used to be the worker's housing. Anyone has any idea what is it?

On the plans they gave us, that is a blank white space with no description.

Here's wishing everyone a Happy Year of the Goat!

CondoWE
18-02-15, 12:48
In front of block 18 there is a metal structure they are building at the site which used to be the worker's housing. Anyone has any idea what is it?

On the plans they gave us, that is a blank white space with no description.

Here's wishing everyone a Happy Year of the Goat!

If I am wrong, near B18 is Pavilion/BBQ pit and near B20 is the tennis court.

1984
18-02-15, 13:20
Just drove by to view again in the day. That metal structure is the shelter for the ramp down into the basement carpark.

radha08
18-02-15, 21:55
happy new year to all sea-estians...:cheers1:

sea esta is looking good now they starting to do landscaping and i hope it turns out beautiful for all of us to enjoy...:jump-for-joy:

CondoWE
19-02-15, 10:16
happy new year to all sea-estians...:cheers1:

sea esta is looking good now they starting to do landscaping and i hope it turns out beautiful for all of us to enjoy...:jump-for-joy:

Wa...bro, you have not been posting any since last year October leh, must be doing something big else where...sibo..:glee::glee::glee:

Anyway....wishing you a happy and joyful GOAT year ahead and hope to meet you at SEA ESTA next MONKEY year...:loyal:!

AG
19-02-15, 18:25
Happy CNY to all sea esta owners....

radha08
19-02-15, 23:42
Wa...bro, you have not been posting any since last year October leh, must be doing something big else where...sibo..:glee::glee::glee:

Anyway....wishing you a happy and joyful GOAT year ahead and hope to meet you at SEA ESTA next MONKEY year...:loyal:!

tks bro same to you best wishes for the year of the goat...i still around bro...busy with some small business venture..but i still watching our beautiful sea esta develop...nowadays see property mkt also scared better venture other things...ha ha:topsy_turvy:

CondoWE
20-02-15, 12:50
tks bro same to you best wishes for the year of the goat...i still around bro...busy with some small business venture..but i still watching our beautiful sea esta develop...nowadays see property mkt also scared better venture other things...ha ha:topsy_turvy:

Yap true...even if market good also cannot put all eggs into a basket.

CondoWE
21-02-15, 18:22
Anyone happen to know the ceiling height for ground floor unit? 2.8-2.9m?

Sea Esta
22-02-15, 02:55
Construction Progress - 21st February 2015 (Part 1)

21st February 2015 - Sea Esta from Pasir Ris Link.
https://scontent-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10984621_636249079815091_49075305231649892_n.jpg?oh=f3dc0b2f728034cf7f42faae6b266812&oe=5592D9AE

21st February 2015 - Block 18 (Road View Units).
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10952123_636249433148389_3074896750335331427_n.jpg?oh=32193d79a11d4de4a12a37ea3d7c6ca2&oe=554D3A27&__gda__=1431265869_d5ef1801b51c65f3403f059271ad688b

21st February 2015 - Block 18 (Pool View Units).
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10610584_636249483148384_8456876401641561086_n.jpg?oh=ff8a94d2ed5864fdeed3286d8cf38774&oe=5591C447&__gda__=1431012909_0a4007e25e2fbcf07b61cd31cea876df

21st February 2015 - Block 20 (Road View Units).
https://scontent-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10997511_636249589815040_7988892449397509797_n.jpg?oh=3c73ec2c557c4802a080be86a4fec288&oe=5556B5E1

21st February 2015 - Block 20 (Pool View Units).
https://scontent-sin.xx.fbcdn.net/hphotos-xfp1/v/t1.0-9/10996545_636249633148369_5374211550137591936_n.jpg?oh=fb981813ae6e8a00f09ce3467f909a87&oe=555504FA

21st February 2015 - Block 22 (Sea View Units).
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10986991_636249719815027_7254816362830894495_n.jpg?oh=78097054f63c6c2f78227839a3305855&oe=554AA87F&__gda__=1431810325_7f3500ed35e3c4624fc47ba5fb0b77af

21st February 2015 - Block 22 (Pool View Units).
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/11009097_636249793148353_4860555547916726838_n.jpg?oh=daffdbe0e1afe0c591c8fd0c394d7404&oe=559681FB&__gda__=1434473105_678db62018418ab9bd9f9edc0682814c

21st February 2015 - Block 26 (Sea View Units).
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/1507956_636249856481680_298828832394547528_n.jpg?oh=ff351af94890ee449e81e68b24a1b272&oe=55574134&__gda__=1435414069_f4a390a9b72c2cf3188ab888770aec52

21st February 2015 - Block 26 (Pool View Units).
https://scontent-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/11021236_636249909815008_2107716138916721624_n.jpg?oh=e029832850ed635a3c4c68c144131153&oe=5594ADE2

21st February 2015 - Block 28 (Sea View Units).
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/11001840_636249976481668_3931646759443848457_n.jpg?oh=2c6213001881d1be36da5834b06fe8e6&oe=5592D669&__gda__=1435452675_5c70861c99034d02ebe998af074acbfb

21st February 2015 - Block 28 (Pool View Units).
https://fbcdn-sphotos-a-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/11015925_636250023148330_92196479584466538_n.jpg?oh=e689e91096f84ced421f2d595cdecd7e&oe=558B8DC0&__gda__=1431162668_40687393bc9624af551a2e5ff2218fba

21st February 2015 - Block 30 (Sea View Units).
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10993447_636250149814984_8124234777391163742_n.jpg?oh=cfbad2b7f332b76f7f82796faa06ab72&oe=558A2932&__gda__=1431308987_cb70672134eb452327714a21eca79d1c

21st February 2015 - Block 30 (Road View Units).
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10985500_636250183148314_370894113804844714_n.jpg?oh=523bc2b5a323694fc005e0fee72f1e66&oe=554B85BE&__gda__=1435099519_ac102b64eac1e1177dc87142168248da

21st February 2015 - Block 24 (Club House).
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10360235_636250296481636_6767919630737258040_n.jpg?oh=7c32385c0aa81f07436eece33718c4a8&oe=5550C2CB&__gda__=1434778529_d3da8c793bcc3070a312cf0da0e816e3

21st February 2015 - The pavilion near the tennis court.
https://scontent-sin.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/10995862_636250483148284_7189929701644041560_n.jpg?oh=34a13fab7a94282f1976515ce77d4b41&oe=559720F6

21st February 2015 - The guard house and the main drop-off area.
https://scontent-sin.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/10404895_636250629814936_5524550135817916695_n.jpg?oh=9351497d1d1a0068f690bb5fe5a9e0a9&oe=558AE478

21st February 2015 - The bin centre and substation.
https://scontent-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10999909_636250889814910_3901606190113963987_n.jpg?oh=047351a7220956e141254196307941ff&oe=5593A877

21st February 2015 - The adventure playground area.
https://scontent-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10991246_636251003148232_477705105285249828_n.jpg?oh=d82d21423da460c18967a6e71589d94e&oe=554BCC92

21st February 2015 - Fence at the junction of Pasir Ris Rise and Jalan Loyang Besar.
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10999794_636251123148220_5561748157937282338_n.jpg?oh=d440dffb7cc6670bfe2fee286119ad9e&oe=55488F3E&__gda__=1430810295_2377361e18dad32f3d69c588b6535641

21st February 2015 - Fence along Pasir Ris Rise.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/11617_636251269814872_5901263537140978044_n.jpg?oh=0eadb83faa12d7f877db552b71831cf6&oe=558725A6&__gda__=1430948315_f49410c5101005c1128501a7cb3ee422

Sea Esta
22-02-15, 02:56
Construction Progress - 21st February 2015 (Part 2)

21st February 2015 - The pedestrian side gate next to the bus stop along Jalan Loyang Besar.
https://scontent-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10991103_636251349814864_7240092619436148393_n.jpg?oh=57d80c3c85698d49ee168c1f6538f6bc&oe=55858891

v_esta
23-02-15, 06:55
Happy Lunar New Year to all neighbours! :)

I was there yesterday. . Really felt like walking in to look see look see around ... hehe.

Good house
24-02-15, 22:40
Nice and looking good :)

hello_forum
25-02-15, 22:46
Clean n nice fencing.. Tink the other one abit messy

ilgr
05-03-15, 09:36
First blood..

SOLD
ON ADDRESS UNIT AREA
(SQFT) SALE PRICE
(S$ PSF) BOUGHT
ON PURCHASE PRICE
(S$ PSF) PROFIT
(S$) HOLDING PERIOD
(DAYS) ANNUALISED
(%)
26 JAN 2015 20 PASIR RIS LINK #XX-XX 517 1,123 6 JUL 2012 945 92,000 934 7.0




MONTH STREET TYPE LOWEST RENTAL
(S$ PSF PM) RENTAL 25TH
(S$ PSF PM) MEDIAN RENTAL
(S$ PSF PM) RENTAL 75TH
(S$ PSF PM) HIGHEST RENTAL
(S$ PSF PM) CONTRACTS
JAN 2015 PASIR RIS LINK NON-LANDED 2.95 3.37 3.78 3.78 3.78 3

AG
09-03-15, 10:54
i have sea view unit in blk 22, area is 1206, high floor . what would be the mkt price if i want to sell this unit?
Any idea / suggestion ?

Sunnielee
09-03-15, 14:52
i have sea view unit in blk 22, area is 1206, high floor . what would be the mkt price if i want to sell this unit?
Any idea / suggestion ?

Mine same blk & area, lower floor. I won't sell it below S$1000psf with reference to the selling price for the past six-months transactions in Seastrand. Our units have much better view and perfect floor plan (good cross ventilation for every room, have windows even for store room and toilets etc) as compared to seastand's.

ilgr
09-03-15, 15:26
i have sea view unit in blk 22, area is 1206, high floor . what would be the mkt price if i want to sell this unit?
Any idea / suggestion ?

Buddy sunnielee sums it up well.

A NUS study observed that the sea view premium is 15% higher at east coast condos.

4BR high floor dual view. Open main door got tri-ventilation. I personally wont let go below 20%.

10004

MrTan
09-03-15, 17:52
sell now can cover ssd, absd, all the fees that came with initial purchase and other costs etc etc, plus a neat profit meh?

DPan
09-03-15, 21:15
SOLDON
26 JAN 2015
UNIT AREA(SQFT)
517
SALE PRICE(S$ PSF)
1,123
BOUGHTON
6 JUL 2012
PURCHASE PRICE(S$ PSF)
945
PROFIT(S$)
92,000
ANNUALISED(%)
7.0

From the above of 7% profit, how to cover back all the duties

invigorated
10-03-15, 09:22
SOLDON
26 JAN 2015
UNIT AREA(SQFT)
517
SALE PRICE(S$ PSF)
1,123
BOUGHTON
6 JUL 2012
PURCHASE PRICE(S$ PSF)
945
PROFIT(S$)
92,000
ANNUALISED(%)
7.0

From the above of 7% profit, how to cover back all the duties

That's an annualized profit. Checking out the 945 paid and 1123 sold psf, works out to about 18% profit.

smellyfish
10-03-15, 09:44
that's 12% SSD + 1% agent fee = $505,114 for sales leg.
assuming 3% stamp duty = $503,221 for purchase leg
- legal fees etc, should be slightly in the red

AG
10-03-15, 12:17
if i get 1200/PSF then i will sell my unit :)

AG
10-03-15, 12:18
if i get 1200/PSF then i will sell my unit

Kukubird
10-03-15, 15:55
if i get 1200/PSF then i will sell my unit

$1,200 sounds reasonable.

But I hope can sell higher.

Waiting for new MRT line near our doorstep.

Anyway I will be staying for at least 2 years before selling.

jxmail00
12-03-15, 15:39
is it true that the last 15% of the loan is disbursed 1 Year after TOP? So we only pay instalment on 85% of loan for the 1st year stay?

usually how long to get keys after project officially TOP? seems to took a long time for our neighbour watercolours ec.

Good house
13-03-15, 10:12
Those TOP delay many time one normally take fast lor becos while waiting touch up n prep finish Liao
Those TOP very fast one take key slower lor, still Hv on going touch up.

KEKEKE....just my humble opinion

CondoWE
15-03-15, 14:23
Car park entrance (green) and Tennis court (still under construction)....

http://i1297.photobucket.com/albums/ag30/CondoWe/Carpark%20entrance_Tennis%20court%20_zps1iyhead0.jpg (http://s1297.photobucket.com/user/CondoWe/media/Carpark%20entrance_Tennis%20court%20_zps1iyhead0.jpg.html)

Sea Esta
15-03-15, 21:25
Construction Progress - 15th March 2015 (Part 1)

15th March 2015 - Sea Esta from Pasir Ris Link.
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10982261_644260582347274_8368871699420733141_n.jpg?oh=2087a8baad5dd4a9eee09fff09b8502b&oe=55B8F22F&__gda__=1438477381_2227d148238e0458634b130328839c6f

15th March 2015 - Block 18 (Road View Units).
https://scontent-sin.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/1926880_644260822347250_5832528562661772251_n.jpg?oh=ea28e63786570b21b59f9b8135cd7f67&oe=5589CBE5

15th March 2015 - Block 18 (Pool View Units).
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/11065877_644260952347237_740573975594126640_n.jpg?oh=8192ade807bc206b875b396fe94d3636&oe=557664E7&__gda__=1435074522_a7ebc90df84243bad606c93ec718f092

15th March 2015 - Block 20 (Road View Units).
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10376274_644261072347225_2670343244628891663_n.jpg?oh=0a966d9afbe517f0012b1074bf901ccf&oe=55B62277&__gda__=1433674013_15e1efa2100d1b272c5c38ddb57692b6

15th March 2015 - Block 20 (Pool View Units).
https://scontent-sin.xx.fbcdn.net/hphotos-xfa1/v/t1.0-9/1508110_644261179013881_6739907300769694495_n.jpg?oh=fa68a08ebe598fbf0cde3679e0a3b34b&oe=55B6638B

15th March 2015 - Block 22 (Sea View Units).
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10986510_644261409013858_8261793326851054902_n.jpg?oh=be0734dab71b8aafd06475da2c1d5395&oe=557C3117&__gda__=1434362749_5e2f0b0cc15cc95e96183ac4d308d7c2

15th March 2015 - Block 22 (Pool View Units).
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/11056089_644261515680514_1017787925527620863_n.jpg?oh=3b9ded70ed380d8392427b0cd2ec2714&oe=5572044F&__gda__=1434215461_889a9bfa43eabaf4c70015b34eba4409

15th March 2015 - Block 26 (Sea View Units).
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10429417_644261642347168_7559011551973740426_n.jpg?oh=50350e4512e7ef702f9f35944c024003&oe=55778CAD&__gda__=1433795349_04702123d30b001b23c87066065e58e3

15th March 2015 - Block 26 (Pool View Units).
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/11050738_644261705680495_4017367053621341312_n.jpg?oh=7c346308fdba03d7426072ede6d88802&oe=557499B6&__gda__=1438209855_d447a16310f322ef44343f18cb146def

15th March 2015 - Block 28 (Sea View Units).
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10363741_644261802347152_3449176150461260970_n.jpg?oh=aec2c3d5d3ee082e9593358b6438d014&oe=55820B83&__gda__=1438081339_f6b70b89fbd1074208ad964511d17646

15th March 2015 - Block 28 (Pool View Units).
https://scontent-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/16902_644262032347129_6878604363722449652_n.jpg?oh=893d30c05f4db749f17e43032a348267&oe=55B37502

15th March 2015 - Block 30 (Sea View Units).
https://scontent-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/11036946_644262152347117_242156398405603832_n.jpg?oh=9d94051f70dc679f344defad63c2b84c&oe=5578D958

15th March 2015 - Block 30 (Road View Units).
https://scontent-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/1743647_644262242347108_39273177918107684_n.jpg?oh=9074f110fedbd0e9075ba5d6d37e6de7&oe=55B57244

15th March 2015 - Block 24 (Club House).
https://fbcdn-sphotos-a-a.akamaihd.net/hphotos-ak-xaf1/v/t1.0-9/13410_644262379013761_921457369987789670_n.jpg?oh=cc4421d781c5fe00dd1707f784007fd6&oe=557B005A&__gda__=1438210463_db266e538c53b421aef4dae1ff500563

15th March 2015 - Sunset Pool with Jacuzzi Seats.
https://scontent-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/11026285_644262645680401_8521054674429130953_n.jpg?oh=87d742bf0a0a3a7156f09dd24b1ae05a&oe=5577F08C

15th March 2015 - Ground Unit of Block 30.
https://scontent-sin.xx.fbcdn.net/hphotos-xap1/v/t1.0-9/10422501_644263029013696_6106312034551976685_n.jpg?oh=03e3a03e8a80076a09ed6cded96b1a3e&oe=5585EE3A

15th March 2015 - Air Con is from Mitsubishi.
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xta1/v/t1.0-9/15806_644263239013675_4962232232705159297_n.jpg?oh=0c41c39ba71b4cc97b65535094afdc7b&oe=5574CBBE&__gda__=1433461629_0679364f49b6b75618efd084e86ae714

15th March 2015 - The Adventure Playground Area.
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10457872_644263739013625_4150533333890611542_n.jpg?oh=1eb9b8405f4ebd0c51cdd9655c581897&oe=55B53410&__gda__=1435011788_bc3c0cdd8eb506108c1a4c1051f3d1c7

15th March 2015 - The Substation.
https://scontent-sin.xx.fbcdn.net/hphotos-xfp1/v/l/t1.0-9/11066066_644263822346950_6950346290558920401_n.jpg?oh=dfec74e33677e3421699743edd290636&oe=55B45109

15th March 2015 - The Construction Details of Sea Esta.
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xap1/v/t1.0-9/10592873_644264585680207_1890397544133915933_n.jpg?oh=fb8243c32ee4f7ca20b4e0320e8f8c6c&oe=557C0637&__gda__=1435098859_e6065ddde950aafdfaba70301eb06a31

Sea Esta
15-03-15, 21:26
Construction Progress - 15th March 2015 (Part 2)

15th March 2015 - Underground Car Park Entrance.
https://scontent-sin.xx.fbcdn.net/hphotos-xfa1/v/t1.0-9/10454307_644265175680148_2815392644092310833_n.jpg?oh=37f26e8934bef4f3a24cab60a8508950&oe=55B46FA3

15th March 2015 - The Location for Sea Esta Signage.
https://scontent-sin.xx.fbcdn.net/hphotos-xaf1/v/t1.0-9/11053667_644265459013453_4946837042038974568_n.jpg?oh=b1e9b9dd0e2732aea94627a818c00cc3&oe=55B93E9D

15th March 2015 - Pavilion beside the Tennis Court.
https://scontent-sin.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/11043158_644265839013415_5612473146997832022_n.jpg?oh=067791779d8fe719bf880e6c29eb4ac6&oe=55813123

15th March 2015 - The Tennis Court Area.
https://scontent-sin.xx.fbcdn.net/hphotos-xfp1/v/t1.0-9/11013346_644266299013369_5741991053122789034_n.jpg?oh=feed59f47d50586853684c30c0f134a9&oe=55B341B0

15th March 2015 - The Tennis Court Close Up.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/10408839_644266522346680_5379708192464533365_n.jpg?oh=83e559a8be2a72fb5a72ec028dbcb177&oe=5579ED68&__gda__=1434520578_8e599d3590b168fa4ca9f478b18c30fd

15th March 2015 - Sea Esta from Ripple Bay.
https://scontent-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10422322_644266875679978_2864315744953981734_n.jpg?oh=290136b2c8f62d29d63bda95475aaff0&oe=5576A754

15th March 2015 - Sea Esta from Ripple Bay Close Up.
https://fbcdn-sphotos-a-a.akamaihd.net/hphotos-ak-xfp1/v/t1.0-9/10986834_644267749013224_7299566665736198991_n.jpg?oh=50872975d65dba5553cf0695d1e3aa89&oe=557F8C65&__gda__=1434502124_cc9f79326cab833f4bbf1526d8d9f9e7

15th March 2015 - Landscaping near Block 22.
https://scontent-sin.xx.fbcdn.net/hphotos-xfa1/v/t1.0-9/10628019_644268002346532_8813936232734837560_n.jpg?oh=232c971f2d7dde122fef12087d6efb4c&oe=55865AD8

15th March 2015 - Landscaping near Block 22 (2).
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xpa1/v/t1.0-9/10481686_644268839013115_1423706807128449277_n.jpg?oh=e335a5d7900d860706719944fd770f01&oe=558A33C2&__gda__=1434657658_5791af6bc7ac74e0ee1b7c96b5ded703

15th March 2015 - Completed Fence of Sea Esta looks nice.
https://scontent-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/11017852_644268609013138_7271909161288971589_n.jpg?oh=7e54479c884b8dbfcf4635df068ceb79&oe=557D15C9

15th March 2015 - Pedestrian Side Gate to the Bus Stop along Jalan Loyang Besar Road.
https://scontent-sin.xx.fbcdn.net/hphotos-xpf1/v/t1.0-9/10422322_644269182346414_7731007435590516465_n.jpg?oh=9f5bc96e5d64b6e8c7f735f17e34cbea&oe=5583E950

15th March 2015 - Block 20 from Junction of Jalan Loyang Besar and Pasir Ris Rise.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xpf1/v/t1.0-9/21232_644269625679703_6092597630679924085_n.jpg?oh=2db72adbe38db88833ef874f85be22f0&oe=5589060F&__gda__=1437970148_f6066b7d8f63d45524a4ed23219f58d6

15th March 2015 - The sea facing units.
https://fbcdn-sphotos-g-a.akamaihd.net/hphotos-ak-xaf1/v/t1.0-9/11071505_644270105679655_6903189684788542510_n.jpg?oh=fd16905265be0bda776640cb54670ef2&oe=55B963E3&__gda__=1438021202_e65bac362fa411c1c324e3162533e9e8

15th March 2015 - The sea facing units (2).
https://scontent-sin.xx.fbcdn.net/hphotos-xpa1/v/t1.0-9/10525674_644270372346295_4687751665905980893_n.jpg?oh=547a6ecc4a6c3d9fd1c300b1b6be1ffd&oe=55B9A3CE

v_esta
16-03-15, 13:41
Really looks like the model in the showroom last time.

gennote
16-03-15, 20:41
Thank you Sea Esta, great pics every time

Yuki
17-03-15, 07:48
Looks awesome. Haiz...

v_esta
17-03-15, 08:20
Looks awesome. Haiz...

Why haiz?? O_o

Yuki
17-03-15, 19:36
Why haiz?? O_o
Didn't buy. Repent now.. :(

DPan
17-03-15, 19:58
Didn't buy. Repent now.. :(
Thought you have buy Stratum / Vue8 ?

CondoWE
17-03-15, 20:09
Didn't buy. Repent now.. :(

There are still many other projects around...no need repent..buyer market now..lol!

v_esta
17-03-15, 20:17
Yah, agree... buyer market now.

Yuki
18-03-15, 19:12
Thought you have buy Stratum / Vue8 ?

Missed sea esta..ripple bay..n Brought vue 8 more ex price..although next to the international school la..

But soooooooo looooonnng to Top..wait until neck long long liao. Btw When did sea esta start construction?

DPan
18-03-15, 20:15
Missed sea esta..ripple bay..n Brought vue 8 more ex price..although next to the international school la..

But soooooooo looooonnng to Top..wait until neck long long liao. Btw When did sea esta start construction?

Should be 25th Oct 2012

v_esta
18-03-15, 21:57
Missed sea esta..ripple bay..n Brought vue 8 more ex price..although next to the international school la..

But soooooooo looooonnng to Top..wait until neck long long liao. Btw When did sea esta start construction?

Why you miss Sea Esta leh?
What made you hesitant to get it? Just curious... :)

Yuki
19-03-15, 22:26
Why you miss Sea Esta leh?
What made you hesitant to get it? Just curious... :)

That time was unsure of whether if we could pay...feel price too high. But when we finally managed to "catch up"...too late liao.

v_esta
22-03-15, 09:49
Woah, we are almost in the same situation. But we have a really nice agent who helped us find a good unit which is almost priced within our means, gave us some space, let us do some maths, gave us good advices & then we finally made up our mind and bought it.

Sea Esta
25-03-15, 04:18
Let's hope can TOP by May 2015.

v_esta
25-03-15, 07:50
Let's hope can TOP by May 2015.

Hehe. .. I definitely hope so too!

But seems like the interiors all not done yet, furniture and fittings, I mean.

Myeast
25-03-15, 12:50
Thank you very much Sea Esta for the nice photo update, I really hope it will top sooooooon......:)

CondoWE
25-03-15, 15:48
Let's hope can TOP by May 2015.

So long it TOP before Sept, I am happy...:friendly_wink:!

v_esta
25-03-15, 15:55
So long it TOP before Sept, I am happy...:friendly_wink:!

Errr... why happy before Sep leh?

CondoWE
27-03-15, 09:55
Errr... why happy before Sep leh?

I think May-Jun TOP may not be possible as there are still many to touch up includes interior and exterior so If it's TOP some where begin July-Sep will a bonus liao..:biggrin-new:!

ilgr
27-03-15, 10:51
I rather they take their time to do up the homes and landscapes now that the exterior construction has completed.

I will be happy to move in before Christmas hahah

BOB
30-03-15, 01:26
I think May-Jun TOP may not be possible as there are still many to touch up includes interior and exterior so If it's TOP some where begin July-Sep will a bonus liao..:biggrin-new:!

Sea Esta data with BCA, they have applied for inspection on 9 Mar?

Plan Ref No. Application Type Status Date/Time View Details
A0712-01111-2011-BP01 APP FOR MODIFICATION-WAIVER OF BUILDG REGULATIONS ISSUE WAIVER LETTER 24/11/2014 21:52:16 -
A0712-01111-2011-BP01 BCA-CSC-APPLN FOR SITE INSPECTION PROCESSING 09/03/2015 22:33:50 -
A0712-01111-2011-BP01 BCA-TOP-APPLN SUSPENDED 09/03/2015 22:38:20 -
A0712-01111-2011-BP01 BP PLAN APPROVAL BP APPROVED 22/05/2012 16:34:41 -
A0712-01111-2011-BP01 PRE SUBMISSION CONSULTATIONS RECEIVED 23/10/2013 18:09:43 -

v_esta
30-03-15, 10:40
OMG!

Why would they apply for site inspection when the exterior seems like not 100% completed?

BOB
30-03-15, 15:53
I have seen BCA information for some other developments. Vacanza and Watercolours received TOP approval from BCA one month after site inspection application. Seastrand, Hedges Park and The Gale received TOP approval from BCA 3 months after site inspection application.

Just go to BCA website and key in build plan number which can be found in our brochure.

https://www.bca.gov.sg/eservice/SubmissionStatus.aspx

CondoWE
30-03-15, 16:04
Sea Esta data with BCA, they have applied for inspection on 9 Mar?

Plan Ref No. Application Type Status Date/Time View Details
A0712-01111-2011-BP01 APP FOR MODIFICATION-WAIVER OF BUILDG REGULATIONS ISSUE WAIVER LETTER 24/11/2014 21:52:16 -
A0712-01111-2011-BP01 BCA-CSC-APPLN FOR SITE INSPECTION PROCESSING 09/03/2015 22:33:50 -
A0712-01111-2011-BP01 BCA-TOP-APPLN SUSPENDED 09/03/2015 22:38:20 -
A0712-01111-2011-BP01 BP PLAN APPROVAL BP APPROVED 22/05/2012 16:34:41 -
A0712-01111-2011-BP01 PRE SUBMISSION CONSULTATIONS RECEIVED 23/10/2013 18:09:43 -


OMG!

Why would they apply for site inspection when the exterior seems like not 100% completed?

Application suspended ?...

CondoWE
30-03-15, 16:21
Latest Sea Esta data with BCA on 15 Mar...

http://i1297.photobucket.com/albums/ag30/CondoWe/Sea%20Esta_zpspjd7f2xk.png (http://s1297.photobucket.com/user/CondoWe/media/Sea%20Esta_zpspjd7f2xk.png.html)

BOB
30-03-15, 16:28
Yah.. the suspended part I noticed in a few of the developments. It happened to Watercolours when they applied on 9/12/2014, then 31/12/2014 it was approved. Similarly for Gale, they apply inspection Oct 2012, TOP was suspended 21/12/2012 but the TOP approval came in Jan 2013:

A1369-00521-2007-BP01 BCA-CSC-APPLN APPROVED 06/07/2013 13:27:23 -
A1369-00521-2007-BP01 BCA-CSC-APPLN FOR SITE INSPECTION DATE CONFIRMED 19/10/2012 13:44:50 -
A1369-00521-2007-BP01 BCA-TOP-APPLN SUSPENDED 26/12/2012 17:31:22

On what it's all about or why they apply when it's not fully done, I got no clue.. :) That's why I checked a few developments where I could obtain their brochure and Building Plan No, and I do see the suspension thingy common. So all I did was just try see a trend among the developments' submissions to BCA.

I also recalled previously from Straits Construction website before they upgraded their website, where they stated construction completion May 2015 (now it's not stated after they revamped their website). If you look at the comment sections at Sea Esta Facebook, a guy keep mentioning that reliable sources told him TOP June/July.

BOB
30-03-15, 16:36
Latest Sea Esta data with BCA on 15 Mar...

http://i1297.photobucket.com/albums/ag30/CondoWe/Sea%20Esta_zpspjd7f2xk.png (http://s1297.photobucket.com/user/CondoWe/media/Sea%20Esta_zpspjd7f2xk.png.html)

You have to add a BP01 at the back of the reference number. If you look at the brochure, at the page with the "Air-Conditioner Schedule" and there is QR Code at the bottom of the page, there are lotsa words at the bottom of the page listing License No, Tenure of Land etc. There is a Building Plan No.10059

BOB
30-03-15, 16:45
I believe the numbers without BP01 is the Project Ref No.
10060

Anyway, in no way I can make confirmation of the TOP. I was just analysing trends and data coz I'm planning my finances ahead.

This Seastrand submission to BCA:

Plan Ref No. Application Type Status Date/Time View Details
A1938-01018-2010-BP01 APP FOR MODIFICATION-WAIVER OF BUILDG REGULATIONS ISSUE WAIVER LETTER 24/07/2014 15:14:26 -
A1938-01018-2010-BP01 BCA-CSC-APPLN FOR SITE INSPECTION DATE CONFIRMED 29/09/2014 14:47:17 -
A1938-01018-2010-BP01 BCA-TOP-APPLN APPROVED 05/12/2014 15:54:28 -
A1938-01018-2010-BP01 BP PLAN APPROVAL BP APPROVED 21/06/2011 17:02:44 -

BOB
30-03-15, 16:51
The image I took from Sea Esta facebook. The brochure does have that number too.

v_esta
30-03-15, 17:43
Wow. Thanks for the info sharing, BOB. I didn't know. Now I know. I also like to plan my finances ahead.

v_esta
30-03-15, 17:49
After all these speculations, I can't wait to jump into the jacuzzi pool now. Haha..

Sunnielee
31-03-15, 14:20
Application suspended ?...

Fingers crossed! From my analysis of TOP application and nos of suspensions, it takes 1+ to 4 months to get final TOP approval. e.g
Seastrand: 1st TOP application, Aug 2014, Top date: Dec 2014
Watercolours:1st TOP application, Oct 2014, Top date: Dec 2014
Hedge Park: 1st TOP application, Nov 2014 (if not wrong), Top date: Jan 2015

I feel that developers just try luck for 1st TOP inspection.

v_esta
31-03-15, 23:54
Fingers crossed! From my analysis of TOP application and nos of suspensions, it takes 1+ to 4 months to get final TOP approval. e.g
Seastrand: 1st TOP application, Aug 2014, Top date: Dec 2014
Watercolours:1st TOP application, Oct 2014, Top date: Dec 2014
Hedge Park: 1st TOP application, Nov 2014 (if not wrong), Top date: Jan 2015

I feel that developers just try luck for 1st TOP inspection.

I think probably the developers are trying to pre empt us that it's going to TOP soon!? =P

ahboy86
03-04-15, 12:02
Yah.. the suspended part I noticed in a few of the developments. It happened to Watercolours when they applied on 9/12/2014, then 31/12/2014 it was approved. Similarly for Gale, they apply inspection Oct 2012, TOP was suspended 21/12/2012 but the TOP approval came in Jan 2013:

A1369-00521-2007-BP01 BCA-CSC-APPLN APPROVED 06/07/2013 13:27:23 -
A1369-00521-2007-BP01 BCA-CSC-APPLN FOR SITE INSPECTION DATE CONFIRMED 19/10/2012 13:44:50 -
A1369-00521-2007-BP01 BCA-TOP-APPLN SUSPENDED 26/12/2012 17:31:22

On what it's all about or why they apply when it's not fully done, I got no clue.. :) That's why I checked a few developments where I could obtain their brochure and Building Plan No, and I do see the suspension thingy common. So all I did was just try see a trend among the developments' submissions to BCA.

I also recalled previously from Straits Construction website before they upgraded their website, where they stated construction completion May 2015 (now it's not stated after they revamped their website). If you look at the comment sections at Sea Esta Facebook, a guy keep mentioning that reliable sources told him TOP June/July.

haha. That guy is me. Well, let's just wait and see. And take the information as a rough gauge. :)

Am also waiting to see how accurate my sources are. :)

jxmail00
03-04-15, 22:49
hi, how much do you all reckon the maintenance fees will cost per share for a development like this?

Sea Esta
05-04-15, 03:19
Construction Progress - 4th April 2015 (Part 1)

4th April 2015 - Sea Esta from Pasir Ris Link.
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xap1/t31.0-8/11074190_653738054732860_1560043608847283636_o.jpg

4th April 2015 - Block 18 (Road View Units).
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xpf1/t31.0-8/11080745_653738298066169_2060478047988838424_o.jpg

4th April 2015 - Block 18 (Pool View Units).
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xpt1/t31.0-8/11075261_653738434732822_7268921340973984743_o.jpg

4th April 2015 - Block 20 (Road View Units).
https://fbcdn-sphotos-e-a.akamaihd.net/hphotos-ak-xap1/t31.0-8/10838143_653738531399479_3079959053003250677_o.jpg

4th April 2015 - Block 20 (Pool View Units).
https://fbcdn-sphotos-c-a.akamaihd.net/hphotos-ak-xfp1/t31.0-8/11080622_653738694732796_5238711311528637021_o.jpg

4th April 2015 - Block 22 (Sea View Units).
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xtf1/t31.0-8/11121222_653738828066116_2184482146642563537_o.jpg

4th April 2015 - Block 22 (Pool View Units).
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xpa1/t31.0-8/11084163_653738948066104_3674485236061276833_o.jpg

4th April 2015 - Block 26 (Sea View Units).
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xfp1/t31.0-8/11035844_653739161399416_5569337820819448901_o.jpg

4th April 2015 - Block 26 (Pool View Units).
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xtf1/t31.0-8/11075305_653739341399398_6362553047281134222_o.jpg

4th April 2015 - Block 28 (Sea View Units).
https://scontent-sin.xx.fbcdn.net/hphotos-xfp1/t31.0-8/11026041_653739454732720_2732313854125027598_o.jpg

4th April 2015 - Block 28 (Pool View Units).
https://scontent-sin.xx.fbcdn.net/hphotos-xfa1/l/t31.0-8/10495984_653739548066044_8185391170753529573_o.jpg

4th April 2015 - Block 30 (Sea View Units).
https://scontent-sin.xx.fbcdn.net/hphotos-xtp1/t31.0-8/11130509_653739664732699_5847065597858377181_o.jpg

4th April 2015 - Block 30 (Road View Units).
https://scontent-sin.xx.fbcdn.net/hphotos-xpa1/t31.0-8/10856786_653739784732687_529180413949196789_o.jpg

4th April 2015 - Block 24 (Club House).
https://scontent-sin.xx.fbcdn.net/hphotos-xap1/t31.0-8/10842313_653739888066010_8410640907222609429_o.jpg

4th April 2015 - Block 24 Alternate View (Club House).
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xtp1/t31.0-8/11096474_653740041399328_8778728395509681847_o.jpg

4th April 2015 - Fence at the junction of Pasir Ris Rise and Jalan Loyang Besar.
https://scontent-sin.xx.fbcdn.net/hphotos-xap1/t31.0-8/11084185_653740418065957_5393666506982112649_o.jpg

4th April 2015 - Workers unloading plants for landscaping.
https://fbcdn-sphotos-d-a.akamaihd.net/hphotos-ak-xap1/t31.0-8/11080663_653740214732644_1446946400627311567_o.jpg

4th April 2015 - Landscaping at Sunset Pool with Jacuzzi Seats.
https://fbcdn-sphotos-h-a.akamaihd.net/hphotos-ak-xap1/t31.0-8/1495998_653741324732533_4352749020145517074_o.jpg

4th April 2015 - Landscaping at the Adventure Park.
https://fbcdn-sphotos-f-a.akamaihd.net/hphotos-ak-xpf1/t31.0-8/11130423_653745228065476_4457237957950947429_o.jpg

4th April 2015 - Landscaping near the Bin Centre and Substation.
https://fbcdn-sphotos-b-a.akamaihd.net/hphotos-ak-xfp1/t31.0-8/11080724_653741568065842_8296408846701760812_o.jpg

Sea Esta
05-04-15, 03:20
Construction Progress - 4th April 2015 (Part 2)

4th April 2015 - Trees near the Entrance.
https://scontent-sin.xx.fbcdn.net/hphotos-xaf1/t31.0-8/11090868_653741958065803_6990631415262178019_o.jpg

4th April 2015 - The Location for Sea Esta Signage.
https://scontent-sin.xx.fbcdn.net/hphotos-xat1/t31.0-8/11114051_653742128065786_848609878503127085_o.jpg

4th April 2015 - The Tennis Court Area.
https://fbcdn-sphotos-a-a.akamaihd.net/hphotos-ak-xat1/t31.0-8/10628633_653742254732440_7859768027376937576_o.jpg

4th April 2015 - The Tennis Court Close Up.
https://scontent-sin.xx.fbcdn.net/hphotos-xfp1/t31.0-8/11008650_653742394732426_8004062136167654908_o.jpg

4th April 2015 - Sea Esta Fence and Ripple Bay Fences.
https://scontent-sin.xx.fbcdn.net/hphotos-xtp1/t31.0-8/11035326_653742541399078_1427539687242556868_o.jpg

4th April 2015 - Trees along Jalan Loyang Besar.
https://scontent-sin.xx.fbcdn.net/hphotos-xta1/t31.0-8/10985070_653743101399022_7408162502487395350_o.jpg

4th April 2015 - Worker doing Landscaping.
https://scontent-sin.xx.fbcdn.net/hphotos-xat1/t31.0-8/11115609_653743271399005_5425411421838139024_o.jpg

4th April 2015 - A very tall tree.
https://scontent-sin.xx.fbcdn.net/hphotos-xta1/t31.0-8/11060993_653744388065560_3114937883400635870_o.jpg

4th April 2015 - The Swimming Pool.
https://scontent-sin.xx.fbcdn.net/hphotos-xap1/t31.0-8/11088819_653744598065539_8928637603682353115_o.jpg

4th April 2015 - The Pedestrian Side Gate along Jalan Loyang Besar.
https://scontent-sin.xx.fbcdn.net/hphotos-xpt1/t31.0-8/11034351_653744901398842_151673253649764980_o.jpg

1984
05-04-15, 13:46
Thanks Sea Esta for all the effort and time spent taking the photos (capturing all the different angles of the project) all these while!

Now with the landscaping in progress, it looks hopeful that we could get our keys by Jul-Sep period:peaceful::peaceful:

CondoWE
06-04-15, 10:31
Thanks bro SE for the pictures...:encouragement:!

gennote
07-04-15, 21:19
Many thanks Sea Esta, always look forward to your postings!

Myeast
07-04-15, 22:04
Thanks a lot for the nice photos, it covered many diff angles of our new home! ��

Sea Esta
09-04-15, 02:34
Folks, you all are welcome. :)

Just doing my part to provide updates on our new home.

Towards TOP. :)

AG
10-04-15, 09:37
Thanks Sea Esta for the pictures

yyenwei
13-04-15, 19:55
last Saturday went to Sea Esta, Straits Construction worker told me, Sea Esta will begin TOP inspections this week. Hooray!!!

Sunnielee
14-04-15, 09:46
last Saturday went to Sea Esta, Straits Construction worker told me, Sea Esta will begin TOP inspections this week. Hooray!!!

Yeah! I went there at Sunday night. The whole site was cleared up with all the construction materials laid outside along the fencing. I suspected the TOP inspection due soon...:glee::glee:

Sea Esta
14-04-15, 13:11
Yeah! I went there at Sunday night. The whole site was cleared up with all the construction materials laid outside along the fencing. I suspected the TOP inspection due soon...:glee::glee:

This is great news. :D

v_esta
14-04-15, 21:22
This is great news. :D

That's not great!
That's better than great!

That's A.W.E.S.O.M.E.! ;) ;)

Haha....

What's BP Plan approval > Processing?

Sea Esta
15-04-15, 01:56
That's not great!
That's better than great!

That's A.W.E.S.O.M.E.! ;) ;)

Haha....

What's BP Plan approval > Processing?

True. :D

CondoWE
15-04-15, 13:14
:applouse::applouse::applouse:!

ilgr
15-04-15, 23:43
Thanks SE for the pictures and yyenwei and sunnielee for the TOP inspection updates!

ahboy86
18-04-15, 11:10
Dear friends / neighbours to be. Some updates from BCA site.

Dropped by the site few days ago, can hear water!

Guess they are testing the pools / cascading waterfalls from the 50m lap pool to the play / fun pool.

Look forward to TOP soon.

v_esta
18-04-15, 12:50
Thanks for the update about the swimming pool testing, ah boy.. it's really making me real excited!

At the same time, means $$ going out real fast too!

radha08
18-04-15, 13:02
Love the landscaping more plants and trees nicer

CondoWE
18-04-15, 13:54
Love the landscaping more plants and trees nicer

hehehe..You can make it more greenery by planting more in your big patio leh...LOL!

radha08
18-04-15, 14:10
hehehe..You can make it more greenery by planting more in your big patio leh...LOL!

Ya got to make the best use of space...get used to new style of living...nowadays no more big big apartment...

v_esta
18-04-15, 19:10
Love the landscaping more plants and trees nicer

Yup. Just went there to see and everything seems ready, maybe except for the kids playground?!
The landscaping looks great.

CondoWE
21-04-15, 17:29
Just being informed by lawyer to release 5% more ...in total 60% liao...TOP coming close :banana: :banana: :banana: !

v_esta
21-04-15, 20:06
Seems like they are left with the common areas not yet inspected.

Sea Esta
23-04-15, 00:33
Just being informed by lawyer to release 5% more ...in total 60% liao...TOP coming close :banana: :banana: :banana: !

Me too. This is getting exciting. TOP next.

radha08
23-04-15, 06:17
Which blocks u guys think will get keys first...or will it be all together

v_esta
23-04-15, 07:46
My guess is altogether?

Our project not so big...

acosean
23-04-15, 08:10
Usually it will be by blocks. Can't remember which block was first to build. That block would usually have their keys released first (via online booking).

Sea Esta
23-04-15, 08:24
Usually it will be by blocks. Can't remember which block was first to build. That block would usually have their keys released first (via online booking).

Blk 20 is the first to be completed during construction.